Contract Change Order and Budgetary Adjustments: Power Inn Queue Cutter Project (T15186000)
End
FileID
File ID: 2024-00702
End
Location
Location: District 6, Represented by Councilmember Guerra
End
Recommendation
Recommendation: Adopt a Resolution: 1) authorizing the City Manager or the City Manager's designee to increase the revenue and expenditure budgets of the Power Inn Queue Cutter Project (T15186000) by $385,700 (Other Capital Grants, Fund 3704); 2) authorizing the City Manager or the City Manager's designee to execute Change Order No. 2 to City Agreement No. C2021-1237 with McGuire & Hester Inc, for an amount not to exceed $250,543, bringing the agreement's total not-to-exceed amount to $1,557,664; and 3) resetting the City Manager's administrative authority to issue Change Orders for City Agreement No. C2021-1237.
End
Contact
Contact: Avtar Banwait, Assistant Civil Engineer, (916) 808-6805, abanwait@cityofsacramento.org; Judy Matsui-Drury, Supervising Engineer, (916) 808-7610, jmatsui-drury@cityofsacramento.org; Ofelia Avalos, Engineering Manager, (916) 808-5054, oavalos@cityofsacramento.org; Department of Public Works
End
Presenter
Presenter: None.
End
Attachments
Attachments:
1-Description/Analysis
2-Resolution
3-Contract Change Order No. 2 - McGuire and Hester
End
Description/Analysis
IssueDetail
Issue Detail: The Power Inn Road Queue Cutter Project (T15186000) will improve vehicular and pedestrian safety at the Power Inn Road Railroad Crossing between 21st Avenue and Fruitridge Road. It will include the construction of a queue cutter traffic signal for southbound automobile traffic, close an existing sidewalk gap on the west side of Power Inn Road, install new railroad warning devices, and construct new concrete paneling to facilitate pedestrian crossings of the railroad tracks.
The Section 130 Railroad-Highway Crossings Program (RHCP), intended to improve crossing safety at at-grade rail crossings, is admini...