Recommendation
Recommendation: Pass a Motion authorizing the City Manager or the City Manager's designee to execute Supplemental Agreement No. 3 to City Agreement 2019-0226 with Kjeldsen, Sinnock & Neudeck Inc. (KSN) to provide additional geotechnical analysis for the Natomas Interior Levees Evaluation & Certification, for an amount not-to-exceed $20,526, bringing the agreement's total not-to-exceed amount to $1,433,509.
End
Contact
Contact: Daniel Smith, Project Manager, (916) 808-7901, dsmith@cityofsacramento.org; Neal Joyce, Supervising Engineer, (916) 808-1912, njoyce@cityofsacramento.org; Sherill Huun, Engineering & Water Resources Division Manager, (916) 808-1455, shuun@cityofsacramento.org; Pravani Vandeyar, Director, (916) 808-3765, pvandeyar@cityofsacramento.org; Department of Utilities
End
Presenter
Presenter: None.
End
Attachments
Attachments:
1-Description/Analysis
2-Supplemental Agreement
End
Description/Analysis
IssueDetail
Issue Detail: Staff recommends Council approve Supplemental Agreement No. 3 with Kjeldsen, Sinnock & Neudeck Inc. (KSN), for performing additional seepage and slope stability analyses and Master Plan review for existing detention basins under variable hydraulic conditions to support levee accreditation and minimize the area that may be mapped into the floodplain by FEMA.
End
PolicyConsiderations
Policy Considerations: The proposed supplemental agreement exceeds the City Manager's approval authority, requiring Council approval.
End
EconomicImpacts
Economic Impacts: None.
End
EnvironmentalConsiderations
Environmental Considerations: This project was determined to be exempt from the require...