Title: Ninos Parkway Phase 2 (K15202000): Budgetary Adjustments, Approval of Plans and Specifications and Contract Award [Published for 10-Day Review 06/14/2024]
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Ninos Parkway Phase 2 (K15202000): Budgetary Adjustments, Approval of Plans and Specifications and Contract Award [Published for 10-Day Review 06/14/2024]
End

FileID
File ID: 2024-01068
End

Location
Location: District 3, Represented by Mayor Pro Tem Talamantes
End

Recommendation
Recommendation: Pass a Resolution: 1) approving the Plans and Specifications for the Ninos Parkway Phase 2 project (K15202000); 2) authorizing the City Manager or the City Manager's designee to transfer $2,500,000 from South Natomas Facility Benefit (Fund 2021) available fund balance to the expenditure budget of the Ninos Parkway Phase 2 project (K15202000); 3) authorizing the City Manager or the City Manager's designee to transfer $150,000 from Transportation Development Impact Fee (Fund 3215) available fund balance to the expenditure budget of the Ninos Parkway Phase 2 project (K15202000); 4) awarding the construction contract for the Ninos Parkway Phase 2 project (K15202000) to Martin Brothers Construction for an amount not to exceed $2,091,000; and 5) authorizing the City Manager or the City Manager's designee to execute the construction contract for the Ninos Parkway Phase 2 project (K15202000) to Martin Brothers Construction.
End

Contact
Contact: Avtar Banwait, Assistant Civil Engineer, (916) 808-6805, abanwait@cityofsacramento.org; Judy Matsui-Drury, Supervising Engineer, (916) 808-7610, jmatsui-drury@cityofsacramento.org; Ofelia Avalos, Engineering Services Manager,
(916) 808-5054, oavalos@cityofsacramento.org; Department of Public Works
End

Presenter
Presenter: None
End

Attachments
Attachments:
1-Description/Analysis
2-Resolution
3-Project Plans
4-Contract: Martin Brothers Construction
End

Description/Analysis
IssueDetail
Issue Detail: In 2004, the City of Sacramento approved the Ninos Parkway Master Plan which envisioned a Class 1 multi-use trail along Ninos Parkway from Northfield Drive to Rio Norte Way, approximately 1/2 mile. Subseque...