Title
Memorial Auditorium Loading Dock Improvements Project (M17100100): Approval of Plans and Specifications and Contract Award
End
FileID
File ID: 2024-01114
End
Location
Location: District 4, Represented by Councilmember Valenzuela
End
Recommendation
Recommendation: Pass a Motion: 1) approving the Plans and Specifications for the Memorial Auditorium Loading Dock Improvements Project; 2) awarding the construction contract for the Memorial Auditorium Dock Improvements Project to B & M Builders, Inc. for an amount not to exceed $622,240 (2018 Transient Occupancy Tax (TOT) Revenue Bond, Fund 6330); and 3) authorizing the City Manager or the City Manager's designee to execute the construction contract for the Memorial Auditorium Loading Dock Improvements Project to B & M Builders, Inc.
End
Contact
Contact: Avtar Banwait, Assistant Civil Engineer, (916) 808-6805, abanwait@cityofsacramento.org; Judy Matsui-Drury, Supervising Engineer, (916) 808-7610, jmatsui-drury@cityofsacramento.org; Ofelia Avalos, Engineering Services Manager, (916) 808-5054, oavalos@cityofsacramento.org; Department of Public Works
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Project Plans
3-Contract: B & M Builders, Inc.
End
Description/Analysis
IssueDetail
Issue Detail: As part of the 2018 Memorial Auditorium Renovation Project, a temporary loading dock was designed and constructed to allow for large productions with multiple large trucks to unload along I Street without disrupting traffic. The temporary loading dock has provided a significant benefit by accommodating large productions, however it eliminated a portion of the adjacent sidewalk and on-street parking. The Memorial Auditorium Loading Dock Improvements Project will construct a new sidewalk to restore the pedestrian path of travel while maintaining the necessary access to the loading dock. The driveway is designed for heavy truck traffic around the loading dock...
Click here for full text