Recommendation
Recommendation: Pass a Motion 1) awarding a construction contract to Pacific Polymers, Inc, DBA American Foam Experts, the lowest responsive and responsible bidder, in an amount not to exceed $259,818 for the 35th Avenue Department of Utilities (DOU) Tool Building Roof Replacement; and 2) authorizing the Interim City Manager or designee to execute the contract specified above.
End
Contact
Contact: Norm Colby, Facilities & Real Property Superintendent, ncolby@cityofsacramento.org, (916) 808-8335; James Christensen, Facilities Manager, jechristensen@cityofsacramento.org,
(916) 808-5863; Department of Public Works
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Contract- Pacific Polymers, Inc. DBA American Foam Experts
End
Description/Analysis
IssueDetail
Issue Detail: The existing roof of the 35th Avenue Tool Building is nearing the end of its useful life and requires replacement. The recommended contract with Pacific Polymers, Inc. DBA American Foam Experts (Pacific Polymers, Inc.) will include partial removal of the existing roof system and related components, and the application of a Tremco Tri-Polymer Alloy (TPA) Membrane Roof that will be adhesively attached to the building.
End
PolicyConsiderations
Policy Considerations: The recommendations in this report are in accordance with the provisions of the City Code Chapter 3.56, which requires City Council approval for contracts over $250,000 or more.
End
EconomicImpacts
Economic Impacts: The recommended contract is expected to create 1.92 jobs (1.22 direct jobs and .70 job through indirect and induced activities) and create $253,717 in total economic output ($162,639 of direct output and another $91,078 of output in indirect and i...