Legislation Details

File #: 2025-02004    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 11/24/2025 In control: City Council - 5PM
On agenda: 1/13/2026 Final action:
Title: Contract Change Order: Franklin Boulevard Complete Street (T15165500)
Attachments: 1. 2025-02004 Contract Change Order: Franklin Boulevard Complete Street (T15165500)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Contract Change Order: Franklin Boulevard Complete Street (T15165500)
End

FileID
File ID: 2025-02004
End

Location
Location: Franklin Boulevard between Sutterville Road/12th Avenue and 32nd Avenue, District 5
End

Recommendation
Recommendation: Pass a Motion authorizing the City Manager or designee to execute construction Contract Change Order No. 4 to City Agreement No. 2024-1493 with George Reed, Inc., for the Franklin Boulevard Complete Street Project (T15165500) for zero-cost change.
End

Contact
Contact: Megan Johnson, Senior Engineer, (916) 808-1967, mejohnson@cityofsacramento.org; Judy Matsui-Drury, Supervising Engineer, (916) 808-7610, jmatsui-drury@cityofsacramento.org; Ofelia Avalos, Engineering Manager, (916) 808-5054, oavalos@cityofsacramento.org; Department of Public Works
End

Presenter
Presenter: None
End

Attachments
Attachments:
1-Description/Analysis
2-Change Order No. 4 to City Agreement No. 2024-1493
End

Description/Analysis
IssueDetail
Issue Detail: The Franklin Boulevard Complete Street Project was formed through a community-driven effort in coordination with local businesses, residents, partner agencies, and the City to transform the roadway into an active transportation corridor that serves all modes of transportation. Franklin Boulevard currently has four travel lanes, a center turn lane, and no bicycle lanes. The existing sidewalks have no landscaping or City street trees, and the pedestrian crossings of the street are long. This project will provide two travel lanes, a center turn lane, and install Class IV separated bikeways (using raised curbs and islands for separation from moving traffic); new and modified traffic signals and intersections; trees, landscaping and irrigation; pedestrian-scale lighting; and accessible sidewalk and curb ramps for all users.

On November 19, 2024, City Council awarded the construction contract to George Reed, Inc (Motion No. 2024-0339). The project construction sched...

Click here for full text