Title
Contract Change Order: Franklin Boulevard Complete Street (T15165500)
End
FileID
File ID: 2025-02004
End
Location
Location: Franklin Boulevard between Sutterville Road/12th Avenue and 32nd Avenue, District 5
End
Recommendation
Recommendation: Pass a Motion authorizing the City Manager or designee to execute construction Contract Change Order No. 4 to City Agreement No. 2024-1493 with George Reed, Inc., for the Franklin Boulevard Complete Street Project (T15165500) for zero-cost change.
End
Contact
Contact: Megan Johnson, Senior Engineer, (916) 808-1967, mejohnson@cityofsacramento.org; Judy Matsui-Drury, Supervising Engineer, (916) 808-7610, jmatsui-drury@cityofsacramento.org; Ofelia Avalos, Engineering Manager, (916) 808-5054, oavalos@cityofsacramento.org; Department of Public Works
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Change Order No. 4 to City Agreement No. 2024-1493
End
Description/Analysis
IssueDetail
Issue Detail: The Franklin Boulevard Complete Street Project was formed through a community-driven effort in coordination with local businesses, residents, partner agencies, and the City to transform the roadway into an active transportation corridor that serves all modes of transportation. Franklin Boulevard currently has four travel lanes, a center turn lane, and no bicycle lanes. The existing sidewalks have no landscaping or City street trees, and the pedestrian crossings of the street are long. This project will provide two travel lanes, a center turn lane, and install Class IV separated bikeways (using raised curbs and islands for separation from moving traffic); new and modified traffic signals and intersections; trees, landscaping and irrigation; pedestrian-scale lighting; and accessible sidewalk and curb ramps for all users.
On November 19, 2024, City Council awarded the construction contract to George Reed, Inc (Motion No. 2024-0339). The project construction sched...
Click here for full text