Title
Marysville Boulevard Vision Zero Quick Build Project (Phase I, T15216300)
End
FileID
File ID: 2026-00371
End
Location
Location: Marysville Boulevard, from Los Robles Boulevard to Harris Avenue, District 2
End
Recommendation
Recommendation: Adopt a Resolution: 1) approving the Plans and Specifications for the Marysville Boulevard Vision Zero Quick Build (Phase 1) Project; 2) authorizing the City Manager or designee to increase the expenditure budget of the Marysville Boulevard Vision Zero Safety Project (T15216300) by transferring $1,000,000 (Major Street Construction, Fund 2007) and $228,356 (Road Maintenance and Rehabilitation, Fund 2036) from the Quick-Build Safety Program (T15255300); 3) awarding the construction contract for the Marysville Boulevard Vision Zero Quick Build (Phase 1) Project to Martin General Engineering, Inc. in an amount not-to-exceed $820,436; and 4) authorizing the City Manager or designee to execute the construction contract for the Marysville Boulevard Vision Zero Quick Build (Phase 1) Project to Martin General Engineering, Inc.
End
Contact
Contact: Judith-Matsui Drury, Supervising Engineer, (916) 808-7610, jmatsui-drury@cityofsacramento.org; Ofelia Avalos, Engineering Manager, (916) 808-5054, oavalos@cityofsacramento.org; Department of Public Works
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Resolution
3-Plans and Specifications - Marysville Boulevard Vision Zero Quick Build (Phase 1) Project
4-Construction Contract - Marysville Boulevard Vision Zero Quick Build (Phase 1) Project - Martin General Engineering, Inc.
End
Description/Analysis
IssueDetail
Issue Detail: The Marysville Boulevard Vision Zero Safety Project (T15216300) is located on Marysville Boulevard between Arcade Boulevard and North Avenue. The project's limits were identified in the Vision Zero Top 5 Corridors Plan as one of the top 5 corridors in the City with the highest number of fatal and...
Click here for full text