Title: [Contract] Richards Boulevard Storm Drainage Improvements [Published for 10-Day Review 08/21/2026]
Attachments: 1. 2026-01311 STAFF REPORT
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
[Contract] Richards Boulevard Storm Drainage Improvements [Published for 10-Day Review 08/21/2026]
End

FileID
File ID: 2026-01311[RN1]
End

Location
Location: District 4
End

Recommendation
Recommendation: Adopt a Resolution: 1) approving the contract plans and specifications for the Richards Boulevard Storm Drainage Improvements Project (W14150700, Fund 6211); 2) awarding the contract to ARB, Inc. for an amount not to exceed $2,141,141; 3) authorizing the City Manager or designee to execute the construction contract with ARB, Inc.; and 4) approving budget related transfers.
End

Contact
Contact: Brett Grant, Supervising Engineer, (916) 808-1413, bgrant@cityofsacramento.org; Michelle Carrey, Engineering & Water Resources Division Manager, (916) 808-1438, mcarrey@cityofsacramento.org; Dalia Fadl, Director, (916) 808-1461, dfadl@cityofsacramento.org; Department of Utilities
End

Presenter
Presenter: None
End

Attachments
Attachments:
1-Description/Analysis
2-Contract
3-Resolution
End

Description/Analysis
IssueDetail
Issue Detail: Staff recommend City Council award a construction contract to ARB, Inc., to install storm drain improvements on Richards Boulevard between Sequoia Pacific Boulevard and North 5th Street. The work will include traffic control, excavating and installing roughly 700 linear feet of 54-inch pipe, multiple junction structures, and restoring the roadway once complete. All work will occur within the City right-of-way, and due to the potential of traffic impacts along Richards Boulevard, all work within Richards Boulevard will be subject to night work. The scope of work for this project exceeds the capacity of City staff and therefore an invitation for bids (IFB) was posted to solicit a qualified contractor to perform the work.

Based on the combination of staff experience and hydraulic modeling, it has been identified that during large and intense rainfall events, areas upstream of the project site are potent...