Title
[Change Order] Power Inn Queue Cutter Project (T15186000)
End
FileID
File ID: 2026-01525
End
Location
Location: District 6
End
Recommendation
Recommendation: Adopt a Resolution: 1) authorizing the City Manager or designee to transfer $70,000 from the Major Streets Construction (Fund 2007) available fund balance to the expenditure budget of the Power Inn Queue Cutter Project (T15186000); 2) authorizing the City Manager or designee to execute Change Order No. 5 to City Agreement No. 2021-1237 with McGuire & Hester Inc, for an amount not-to-exceed $85,958, bringing the agreement's total not-to-exceed amount to $1,743,539; and 3) resetting the City Manager's administrative authority to issue Change Orders for City Agreement No. 2021-1237.
End
Contact
Contact: Avtar Banwait, Assistant Civil Engineer, (916) 808-6805, abanwait@cityofsacramento.org; Matthew Johns, Supervising Engineer, (916) 808-5760, mjohns@cityofsacramento.org; Ofelia Avalos, Engineering Services Division Manager, (916) 808-5054, oavalos@cityofsacramento.org; Department of Public Works
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Resolution
3-Contract Change Order No. 5 - McGuire and Hester
End
Description/Analysis
IssueDetail
Issue Detail: The Power Inn Road Queue Cutter Project (T15186000) will improve vehicle and pedestrian safety at the Power Inn Road railroad crossing between 21st Avenue and Fruitridge Road. It will include the construction of a queue cutter traffic signal for southbound automobile traffic, close an existing sidewalk gap on the west side of Power Inn Road, install new railroad warning devices, and construct new concrete paneling to facilitate pedestrian crossings of the railroad tracks.
The project is funded with Federal Section 130 funds administered by Caltrans and is intended to improve crossing safety at at-grade rail crossings. The Section 130 Railroad-Highway Crossings Program (RHCP) is managed...