Title
[Contract Supplement] Budgetary Adjustments and Supplemental Services Agreement for the Sacramento River Parkway Project (K15185000) [Published for 10-Day Review 09/30/2026]
End
FileID
File ID: 2026-01627
End
Location
Location: District 7
End
Recommendation
Recommendation: Adopt a Resolution: 1) authorizing the City Manager or designee to increase the revenue and expenditure budgets of the Sacramento River Parkway Project (K15185000) by $2,970,000 (Federal Capital Grants, Fund 3703); 2) authorizing the City Manager or designee to execute Supplemental Agreement No. 13 to City Agreement No. 2022-0035 with Wood Rodgers, Inc. in an amount not-to-exceed $2,322,124, for a new not-to-exceed amount of $3,098,424; and 3) resetting the City Manager or designee’s administrative authority to issue supplemental agreements with Wood Rodgers, Inc. for City Agreement No. 2022-0035.
End
Contact
Contact: Jesse Gothan, Supervising Engineer, (916) 808-6897, jgothan@cityofsacramento.org; Ofelia Avalos, Engineering Services Division Manager, (916) 808-5054, oavalos@cityofsacramento.org; Department of Public Works
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Resolution
3-Professional Services Agreement
End
Additional Description/Analysis
IssueDetail
Issue Detail: In 1975, the Sacramento City Council adopted the Feasibility Study and Sacramento River Parkway Master Plan, establishing a vision for public recreational access along the Sacramento River from Freeport to the American River confluence while protecting and enhancing natural resources. The 1997 Sacramento River Parkway Plan Update preserved the ultimate vision for an off-street, multi-use riverfront trail. It also addressed surrounding land uses, security, privacy, and design. The City Council approved the plan’s Environmental Impact Report on October 21, 1997.
The American and Sacramento River Parkway Plans 2012 Implementation Program was appr...
Click here for full text