Legislation Details

File #: 2026-01666    Version: 1
Type: Consent Item - 10 Day Contract Status: Agenda Ready
File created: 8/31/2026 In control: City Council - 2PM
On agenda: 10/13/2026 Final action:
Title: [Contract Amendment] Del Rio Sewer Force Main Rehabilitation [Published for 10-Day Review 09/30/2026]
Attachments: 1. 2026-01666 STAFF REPORT
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
[Contract Amendment] Del Rio Sewer Force Main Rehabilitation [Published for 10-Day Review 09/30/2026]
End

FileID
File ID: 2026-01666
End

Location
Location: District 7
End

Recommendation
Recommendation: Pass a Motion: 1) authorizing the City Manager or designee to execute Change Order No. 1 to City Agreement No. 2026-0179 with Insituform Technologies, LLC, for the Combined Sewer System Pipe Program (X14170100; Fund 6206), for an amount not to exceed $2,331,084, bringing the agreement’s total not-to-exceed amount to $19,297,287; and 2) resetting the City Manager or designee’s authority to issue contract amendments for the Agreement.
End

Contact
Contact: Angelo Vasquez, Project Manager, (916) 808-1701, arvasquez@cityofsacramento.org; Michelle Carrey, Engineering & Water Resources Division Manager, (916) 808-1438, mcarrey@cityofsacramento.org; Dalia Fadl, Director, (916) 808-3765, dfadl@cityofsacramento.org; Department of Utilities
End

Presenter
Presenter: None
End

Attachments
Attachments:
1-Description/Analysis
2-Change Order
End



Additional Description/Analysis
IssueDetail
Issue Detail: Staff recommends City Council approve Change Order No. 1 with Insituform Technologies, LLC on Agreement No. 2026-0179, to compensate the Contractor for performing additional work associated with increasing the liner thickness on the Cured in Place Pipe (CIPP) process on the 72-inch Force Main Rehabilitation, adding carbon filtration to filter out the styrene concentration in the cured water from the CIPP process, and crediting the City of Sacramento (City) for unused lining launch and reception pit locations. This work included, but was not limited to, increased material costs, additional effort to accommodate the thicker liner installation, installation of the carbon filtration process, and additional traffic control. The total cost, including the credit, of this work is $2,331,084, which was determined using the City Standard Specification...

Click here for full text