Title
[Contract Amendment] Freeport Reservoir Pump Replacement and Improvement Project
End

FileID
File ID: 2026-01726
End

Location
Location: Citywide
End

Recommendation
Recommendation: Pass a Motion: 1) authorizing the City Manager or designee to execute Change Order No. 6 to City Agreement No. 2023-1349 with TNT Industrial Contractors, Inc., for the Reservoir Rehabilitation Program (Z14130500, Fund 6005), for an amount not to exceed $69,588 bringing the agreement’s total not-to-exceed amount to $5,321,803; and 2) resetting the City Manager or designee’s authority to issue contract amendments for the Agreement.
End

Contact
Contact: James Yorita, Project Manager, (916) 808-1911, jyorita@cityofsacramento.org; Michelle Carrey, Engineering & Water Resources Division Manager, (916) 808-1438, mcarrey@cityofsacramento.org; Dalia Fadl, Director, (916) 808-3765, dfadl@cityofsacramento.org; Department of Utilities
End

Presenter
Presenter: None
End

Attachments
Attachments:
1-Description/Analysis
2-Contract Amendment
End

Description/Analysis
IssueDetail
Issue Detail: Staff recommends City Council approve Change Order No. 6 with TNT Industrial Contractors, Inc. for the City Agreement No. 2023-1349 to compensate the Contractor for performing additional work related to the Freeport Reservoir Pump Replacement and Improvement Project.

This work performed between December 1, 2025, and August 17, 2026, included, but was not limited to, preparatory activities for future reservoir repairs, installation of a new water quality analyzer, overflow switch, door threshold, and new security doors. The change order also balances eliminated contract items and reconciles the final contract amount based on actual work completed during construction.

The work in Change Order No. 6 covers design changes and work required to address existing conditions found during construction. While City could have performed some of the work, doing so would have resulted in c...