Title
[Contract Amendment] Change Order: Del Paso Blvd Infrastructure Needs
End
FileID
File ID: 2026-01969
End
Location
Location: Citywide
End
Recommendation
Recommendation: Adopt a Resolution: 1) authorizing the City Manager or designee to execute Change Order No. 5 to City Agreement No. 2025-0769 with Soracco, Inc. for the Separated Sewer Pipe Program (X14160500), for an amount not to exceed $229,256, bringing the agreement’s total not-to-exceed amount to $4,148,869; 2) approving a budget transfer of $243,057 from the Transportation Corridor Program FY20 (R15200000, Fund 2036) to the Separated Sewer Pipe Program (X14160500); 3) and ratifying all previous contract amendments executed pursuant to the City Manager’s delegated authority to execute contract amendments and thus resetting the City Manager’s or designee’s authority to issue change orders for City Agreement No. 2025-0769 .
End
Contact
Contact: Kyle Beltran, Project Manager, (916) 808-3828, kbeltran1@cityofsacramento.org; Michelle Carrey, Engineering & Water Resources Division Manager, (916) 808-1438, mcarrey@cityofsacramento.org; Dalia Fadl, Director, (916) 808-3765, dfadl@cityofsacramento.org; Department of Utilities
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Change Order
3-Resolution
End
Additional Description/Analysis
IssueDetail
Issue Detail: Staff recommends City Council approve Change Order No. 5 with Soracco, Inc. for the City Agreement No. 2025-0769, to compensate the Contractor for performing additional work associated with upsizing the casing pipe for bore and jack operations, resolving and supporting unforeseen utility conflicts during the construction of the sewer improvement project, raising and lowering utility iron due to extended asphalt restoration efforts, and increasing the amount of asphalt tonnage for surface restoration. This work included, but was not limited to, additional material costs, labor, potholing, saw cutting, excavation, shoring, support, traffic control, backfill, and surface restoration. The total cost of this work is $229,256, which was determined using the City Standard Specifications for Public Construction Section 4-4, “Changes in the Work” and Section 8-10, “Payment by Cost and Percentage”.
In April 2026, the City of Sacramento (City) determined that the proposed 36-inch casing pipe for the boring and jacking efforts beneath Del Paso Road would not provide adequate space to properly install blown sand around the 24-inch carrier sewer pipe and its casing spacers based on the material submittals by the Contractor. Therefore, the Contractor was directed to increase the casing pipe size from 36 inches to 42 inches to provide proper installation during bore and jack operations.
Between May 28 and June 11, 2026, the Contractor encountered multiple underground utility conflicts near Lochbrae Road, including water, gas, communication lines, and an asbestos water main. This change order compensates the Contractor for relocating the sewer manhole to avoid these conflicts.
During the construction phase, members of the public raised concerns with Public Works and the City Councilmember regarding the poor pavement conditions along Edgewater Road. As a result, Public Works re-evaluated the pavement conditions and determined that limited structural rehabilitation was needed, as the Pavement Condition Index (PCI) was below 50. In Fall 2026, the City directed the Contractor to perform additional pavement restorations beyond the scope required for sewer-related impacts, including additional asphalt tonnage and raising and lowering utility iron elevations.
End
PolicyConsiderations
Policy Considerations: This Change Order exceeds the City Manager’s approval authority and requires Council approval pursuant to City Code section 3.04.020.
End
EconomicImpacts
Economic Impacts: This project is expected to create 0.90 total jobs (0.52 direct jobs and 0.38 jobs through indirect and induced activities) and create $138,308.52 in total economic output ($87,176.92 of direct output and another $51,131.60 of output through indirect and induced activities).
The indicated economic impacts are estimates calculated using a calculation tool developed by the Center for Strategic Economic Research (CSER). CSER utilized the IMPLAN input-output model (2009 coefficients) to quantify the economic impacts of a hypothetical $1 million of spending in various construction categories within the City of Sacramento in an average one-year period. Actual impacts could differ significantly from the estimates and neither the City of Sacramento nor CSER shall be held responsible for consequences resulting from such differences.
End
EnvironmentalConsiderations
Environmental Considerations: This project was reviewed and determined to be categorically exempt from the California Environmental Quality Act (CEQA) under Section 15302. This project includes removing and replacing existing separated sewer mains (utility systems) involving negligible expansion of capacity (CEQA Guidelines Section 15302 (c)).
End
Sustainability
Sustainability: The project is consistent with the 2040 General Plan goal PFS-3.3, “Development Impacts”, as it improves infrastructure reliability and addresses capacity needs within the existing separated sewer system to best support new development. The area within Sewer Basin G304 and G305 has been identified by the Planning Department as a primary redevelopment area and will benefit from this project’s sewer capacity improvements. In response to this designation, along with maintenance issues, a wastewater master plan for Basin G304/G305 was completed in June 2018 by Woodard & Curran.
End
Commission/Committee Action
Commission/Committee Action: Not applicable.
End
RationaleforRecommendation
Rationale for Recommendation: Change Order No. 5 is needed to provide compensation for the additional construction activities performed between April 23, 2026, and October 7, 2026, while the City and Soracco, Inc. addressed unforeseen conditions, implemented design changes, and constructed improvements and pavement restoration along Edgewater Road. The value of Change Order No. 5 exceeds the approval authority of the City Manager as the sum of all contract amendments for this agreement exceed 8% of the original contract value (City Code section 3.04.020.A.3).
Additionally, the budget moves are necessary to compensate the Contractor for the additional pavement restoration work associated with Public Works responsibility. Change Order No. 4 was approved for $245,738, of which $108,879 would fall under Public Works responsibility. Change Order No. 5 is for $229,256, of which $134,178 would fall under Public Works responsibility. The total amount of Public Works responsibility is $243,057.
End
FinancialConsiderations
Financial Considerations: The original not-to-exceed amount of the contract was $3,308,182. The net change by previous change orders in the amount of $611,431 increased the contract not-to-exceed amount to $3,919,613. Proposed Change Order No. 5 in the amount of $229,256 would increase the contract not-to-exceed amount to $4,148,869.
Due to the increased scope of work that was added to the surface restoration between the previous Change Order No. 4 and Change Order No. 5, and because these additional surface improvements are not directly attributable to the impacts of the sewer work, Proposition 218 restricts the use of sewer utility rate funds to pay for these costs. Sewer rate revenues may only be used for activities and improvements that are necessary for providing sewer service and cannot be applied to surface restoration work that exceeds what is required to restore conditions impacted solely by the sewer main construction.
As a result, a budget transfer from the Public Works Department to the Utilities project is required to cover the portion of the surface restoration work that goes above and beyond the sewer-related impacts. The proposed transfer below will ensure that costs are allocated appropriately and in compliance with Proposition 218 requirements, while allowing the project to complete the enhanced surface restoration included in Change Order No. 5.
|
Name |
Project No. |
Fund No. |
Amount (USD) |
|
Transportation Corridor Program FY20 |
R15200000 |
2036 |
($243,057) |
|
Separated Sewer Pipe Program |
X14160500 |
|
$243,057 |
Sufficient funding exists in the Separated Sewer Pipe Program (X14160500) to support the increase to Contract No. 2025-0769 for Change Order No. 05. Additionally, sufficient funding exists in the Transportation Corridor Program FY20 (R15200000) to support the transfer of funds to the Separated Sewer Pipe Program (X14160500).
End
LocalBusinessEnterprise
Local Business Enterprise (LBE): Soracco, Inc. is not an LBE but has partnered with Pace Supply Corp, Anrak Corp, and APS Environmental for this project to exceed the minimum LBE participation requirement. Pace Supply Corp will provide sewer pipe material. Anrak Corp will provide asphalt grinding services. APS Environmental will provide closed-circuit television (CCTV) services.
End
Background
Background: The Del Paso Boulevard Infrastructure Needs Project includes sewer improvements along Edgewater Road to address capacity deficiencies identified in the City’s Basin G304/G305 Master Plan. These improvements will increase system capacity during peak wet-weather events, reduce sewer surcharge and overflow risks, and support residential and commercial development in the Del Paso Boulevard area. This project includes, but is not limited to, sewer pipe upsizing, manhole replacement, sewer service improvements, traffic control, excavation, shoring, backfilling, and surface restoration.
A total of four contract change orders (CCO) have been executed to date, as summarized below.
|
Change Order |
Change Order Amount |
Cumulative Contract Amount |
|
Original Contract |
$ 0 |
$ 3,308,182 |
|
CCO 01 |
$ 187,881 |
$ 3,496,063 |
|
CCO 02 |
$ 72,859 |
$ 3,568,922 |
|
CCO 03 |
$ 104,953 |
$ 3,673,875 |
|
CCO 04 |
$ 245,738 |
$ 3,919,613 |
CCO No. 01 addressed additional work and delays due to unforeseen utility conflicts during sewer construction, including manhole rehabilitation and bypass pumping at Arden Way and El Monte Avenue Alley, water main conflict in Acoustic Alley, and several utility conflict work in Sump 85 Alley. This change order was executed on November 3, 2025.
CCO No. 02 included additional work for unforeseen utility conflicts and other various items encountered during installation of the 15-inch sewer main along Edgewater Road, between Sump 85 Alley and Redwood Avenue. These items included the removal and disposal of abandoned asbestos cement force main in conflict with the sewer alignment, additional work to remove an unmarked buried reinforced concrete slab, repair of a leaking sewer service lateral, and the additional work to support the existing 21-inch force main that was adjacent to the newly installed sewer main. This change order was executed on March 20, 2026.
CCO No. 3 provided compensation for additional work resulting from unforeseen utility conflicts encountered during installation of the 15-inch sewer main along Edgewater Road between Redwood Avenue and Altos Avenue. Work included excavation, potholing, shoring, support, and backfill to protect and maintain existing underground facilities, including a 21-inch force main, 8-inch water main, gas mains, communication conduits, and other conflicting utilities. The additional work was necessary to address trench instability, utility undermining, and conflicts with unmarked utilities. The value of CCO No. 03 exceeded the approval authority of the City Manager as the sum of all contract amendments for this agreement exceeded 8% of the original contract value (City Code 3.04.020.A.3). This change order was approved by City Council on May 12, 2026, and fully executed on May 27, 2026.
CCO No. 4 provided pavement restoration along Edgewater Road, including full-width slurry seal, asphalt milling, and localized full-depth asphalt repairs. The change order also included additional work associated with relocating a manhole to accommodate existing utility conflicts at Lochbrae and Acoustic Alley. This change order was executed on August 10, 2026.
During implementation of CCO No. 4, additional pavement restoration needs were identified that were unforeseen at the time Change Order No. 4 was approved and are addressed under Change Order No. 5.
Proposition 218, adopted by California voters in 1996, amended the State Constitution to ensure that property-related fees-such as sewer rates-are tightly regulated and cannot exceed the proportional cost of providing the related service. It also restricts local governments from using utility rate revenues for purposes unrelated to the service those rates fund, reinforcing a clear boundary between utility operations and general governmental improvements. These requirements are intended to prevent ratepayers from subsidizing activities that do not directly benefit the utility service they receive.
End