Title
[Contract] Martin Luther King Jr. Library Renovation Construction Contract (C15000840)
End
FileID
File ID: 2026-01650
End
Location
Location: 7340 24th Street Bypass, District 8
End
Recommendation
Recommendation: Pass a Motion: 1) authorizing the City Manager or designee to execute Contract Amendment No. 7 to Contract No. 2024-0191 with Swinerton Builders, for an amount not-to-exceed $205,723 for a new total amount not-to-exceed $11,474,571; and 2) resetting the City Manager’s authority to issue change orders.
End
Contact
Contact: Nadia Melgoza, Senior Architect, (916) 808-2262, nmelgoza@cityofsacramento.org; David Avila, Supervising Architect, (916) 808-7501, dravila@cityofsacramento.org; James Christensen, Facilities Manager, (916) 808-5863, jechristensen@cityofsacramento.org, Department of Public Works
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Construction Contract- Swinerton Builders
End
Description/Analysis
IssueDetail
Issue Detail: The Martin Luther King, Jr. (MLK) Library, named in honor of the civil rights leader, is a branch of the Sacramento Public Library System located in South Sacramento. Opened in 1970, this single-story library spans 15,000 square feet, plus a 10,000 square feet maintenance basement. It offers a range of programs and services such as children’s story time, computer classes, and job search assistance.
As a popular community resource, the MLK Library required significant repairs and upgrades to address aging infrastructure and improve its functionality. The remodel was essential to modernize the facility, improve energy efficiency, and create a more functional, accessible, and welcoming environment for the community. The renovation also improved the overall layout, allowing the library to better accommodate its programs, services, and patrons.
On March 5, 2024, the pre-construction phase of a design-assist contract (No. 2024-0191) for the Martin Luther King Jr Library Modernization Project (C15000840) was awarded to Swinerton Builders following a Request for Qualifications (RFQ) process, and on February 4, 2025, Contract Supplement No. 1 was executed to include the construction phase for $10,554,658, and increase the City Manager’s change order authority to 6% of the new not-to-exceed amount.
Throughout construction, changes were made to the contract documents to support the successful renovation and operation of the facility. The majority of the change order work resulted from client-requested modifications that were incorporated to improve the building’s functionality, efficiency, and overall operation. Contract Amendment No. 7 will exceed the City Manager’s authority, and City Council approval is necessary to approve the contract change and complete construction.
End
End
PolicyConsiderations
Policy Considerations: The recommendations in this report are in accordance with the provisions of the City Code Chapter 3.04.020, which requires City Council approval when the sum of all contract amendments executed by the city manager exceeds 6% of the original contract price.
End
EconomicImpacts
Economic Impacts: The recommended contract is expected to create 1.5 jobs (.95 direct jobs and 0.55 jobs through indirect and induced activities) and create $197,895 in total economic output ($126,856 of direct output and another $71,039 of output in indirect and induced activities).
The indicated economic impacts are estimates calculated using a calculation tool developed by the Center for Strategic Economic Research (CSER). CSER utilized the IMPLAN input-output model (2009 coefficients) to quantify the economic impacts of a hypothetical $1 million of spending in various construction categories within the City of Sacramento in an average one-year period. Actual impacts could differ significantly from the estimates and neither the City of Sacramento nor CSER shall be held responsible for consequences resulting from such differences.
End
EnvironmentalConsiderations
Environmental Considerations: The action is exempt from review under the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines, Section 15301. The action involves the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, or mechanical equipment, involving negligible or no expansion of use beyond that existing at the time of the lead agency's determination. The exemption covers interior or exterior alterations involving such things as interior partitions, plumbing, and electrical conveyances; and similar facilities; restoration or rehabilitation of deteriorated or damaged structures, facilities, or mechanical equipment to meet current standards of public health and safety, unless it is determined that the damage was substantial and resulted from an environmental hazard such as earthquake, landslide, or flood. The project qualifies for a Categorical Exemption under Article 19 of CEQA Guidelines Section 15301, existing facilities. The project qualifies for a Categorical Exemption under Article 19 of CEQA Guidelines Section 15301, existing facilities. No environmental review is necessary.
End
Sustainability
Sustainability: Not applicable.
End
Commission/Committee Action
Commission/Committee Action: Not applicable.
End
RationaleforRecommendation
Rationale for Recommendation:
The renovation of the MLK Library is both necessary and long overdue. Approval of Contract Amendment No. 7 will help facilitate the successful completion of the MLK Library Renovation Project.
End
FinancialConsiderations
Financial Considerations: Sufficient funding is available in the MLK Library Renovation Project,(C15000840, Fund 1001) to add Contract Amendment No. 7 for $205,723 to Swinerton Builders Contract No. 2024-0191, with a new amount not-to-exceed $ 11,474,571 and have sufficient remaining funds to complete the project.
End
LocalBusinessEnterprise
Local Business Enterprise (LBE): Swinerton Builders is an LBE.