Title

[Change Order] Construction Change Order and Authority Reset: Franklin Boulevard Gap Closure Project (R15200000)

End

 

FileID

File ID: 2026-01754

End

 

Location

Location: Franklin Boulevard from Mack Road to A Parkway, District 5

End

 

Recommendation

Recommendation: Pass a Motion: 1) Authorizing the City Manager or designee to execute Change Order No. 3 to the City Agreement No. 2025-0650 with O.C. Jones & Sons, Inc. for an amount not to exceed $383,444, bringing the agreement’s not-to exceed amount to $4,166,973; and 2) Resetting the City Manager’s administrative authority to issue Change Orders for the City Agreement No. 2025-0650.

End

 

Contact

Contact: Kelli Lacy, Project Manager, (916) 808-8157, kelacy@cityofsacramento.org; Matthew Johns, (916) 808-5760, mjohns@cityofsacramento.org; Ofelia Avalos, Engineering Services Division Manager, (916) 808-5054, oavalos@cityofsacramento.org; Department of Public Works

End

 

Presenter

Presenter: None

End

 

Attachments

Attachments:

1 - Description/Analysis

2 - Construction Change Order No. 3 to City Agreement 2025-0650

End

 

 

 

Additional Description/Analysis

IssueDetail

Issue Detail: Franklin Boulevard is a major arterial corridor that serves various community spaces and connects neighborhoods. From Mack Road to A Parkway, the project installed buffered Class II bikeways, modified signals, performed road rehabilitation and incorporated other enhancements to ease pedestrian use and reduce biking stress. The Franklin Gap Closure Project fills the gap in active transportation improvements constructed by the City and the County on Franklin Boulevard.

 

Separately, the City of Sacramento’s Last Mile Project is expanding broadband internet to over 4,000 residential units in underserved neighborhoods through the installation of essential fiber-optic infrastructure to bridge the digital divide across Sacramento.

 

In coordination with Sacramento County and the City’s Last Mile Project, new fiber and conduit was installed north of the project limits to connect to the County’s fiber infrastructure and the Sacramento Fire Station No. 56.

 

Change Order No. 1 in the amount of $1,705 has been executed to address County comments on the electrical plans received after construction contract award, which added electrical work to the project and addressed the delayed issuance of the Notice to Proceed.

 

Change Order No. 2 in the amount of $241,705 has been executed to balance bid items above and below the bid quantities due to unforeseen conditions, as well as address additional pavement work and utility adjustments.

 

Change Order No. 3 in the amount of $383,444 will place fiber optic infrastructure in support of the City of Sacramento’s Last Mile Project along Franklin Boulevard from Florin Road to 47th Avenue.

End

 

PolicyConsiderations

Policy Considerations: The actions requested herein are consistent with the City’s goals of improving and expanding public safety and enhancing livability. Specific General Plan goals the project addresses are as follows:

 

M-1.11 Increasing bicycling and walking. The City shall strive to increase bicycling and walking citywide so that it can meet its equity, reduced vehicle miles traveled and sustainability goals.

 

M-1.18 Bicycle Safety. When designing projects, the City shall prioritize designs that strengthen the protection of people bicycling such as improvements that increase visibility of bicyclists, increase bikeway widths, raise bikeways design safer intersection crossings and turns, and separate bikeways from driving traffic wherever feasible.

 

PFS-6.5 Broadband Access. The City shall work to expand broadband internet access throughout Sacramento, prioritizing efforts to improve access for students, residents, and business in disadvantaged communities. Strategies may improve the following:

•                     Expanding the City's middle-mile conduit and fiber optic network to provide opportunities for broadband service providers to leverage city infrastructure in underserved areas.

This Change Order exceeds the City Manager’s approval authority and requires Council approval.

End

 

EconomicImpacts

Economic Impacts: This new infrastructure is expected to create 1.53 total jobs (0.88 direct jobs and 0.65 jobs through indirect and induced actives) and create $236,751.75 in total economic output ($149,226.44 of direct output and another $87,525.31 of output through indirect and induced activities).

End

 

EnvironmentalConsiderations

Environmental Considerations:

California Environmental Quality Act (CEQA):  The Community Development Department, Environmental Planning Services Division has determined that Franklin Boulevard Gap Closure and the Last Mile Project are categorically exempt from the provisions of the California Environmental Quality Act (CEQA) under Categorical Exemption-State Class 1 & 3 and Section Number(s) 15301(c) and 15303.

 

Projects exempted under Class 1 & 3 and Section Number(s) 15301(c) and 15303 consists of the operation, repair, or minor alteration of public streets, sidewalks, gutters, bicycle lanes, and similar facilities involving no expansion of use [15301(c)]. The project also consists of the construction, location, and installation of new small equipment (15303). There would be no significant effect on the environment.

End

 

Sustainability

Sustainability: The project is consistent with the City’s General Plan goals of promoting walking by developing a universally accessible, safe, convenient, integrated, and well-connected pedestrian system. Transportation is also responsible for 57% of Sacramento’s local greenhouse gas emissions, the single largest sector. Providing safe and bikeable transportation alternatives helps to reduce single-occupant vehicle use and contribute towards Sacramento’s climate change goals.

End

 

Commission/Committee Action

Commission/Committee Action: None

End

 

RationaleforRecommendation

Rationale for Recommendation: Change Order No. 3 is a reasonable cost, and the work is necessary to complete the construction project as intended. Staff recommend Council approve Change Order No. 3 to City Agreement No. 2025-0650 with O.C. Jones & Sons, Inc.

End

 

FinancialConsiderations

Financial Considerations: The estimated total cost to complete construction for the Franklin Boulevard Gap Closure Project (R15200000) is $4,166,974. Sufficient funding exists in the remaining allocated budget for the project to execute Change Order No. 3 with O.C. Jones & Sons, Inc. for $383,445.

End

 

LocalBusinessEnterprise

Local Business Enterprise (LBE): O.C. Jones & Sons, Inc. is not an LBE but has partnered with two LBEs for this project to exceed the minimum LBE participation requirement.