Title: Budgetary Adjustments and Authorization to File Clean Energy Credits: Electric Vehicle Blueprint Phase II Project (C15210000)
Attachments: 1. 2026-01896 STAFF REPORT
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Budgetary Adjustments and Authorization to File Clean Energy Credits: Electric Vehicle Blueprint Phase II Project (C15210000)

End

 

FileID

File ID: 2026-01896

End

 

Location

Location: Citywide

End

 

Recommendation

Recommendation: Adopt a Resolution authorizing the City Manager or designee to: 1) file for and accept $59,574 from Internal Revenue Service Clean Energy elective payment funds for eligible City electric vehicle charging infrastructure; and 2) increase the revenue and expenditure budget in the Electric Vehicle Blueprint Phase II Project (C15210000) by $59,574 (Federal Capital Grant, 3703).

End

 

Contact

Contact: Sarah Kolarik, Sustainability Specialist, (916) 808-1421, skolarik@cityofsacramento.org; Rachel Patten, Sustainability Manager, (916) 808-5016, rpatten@cityofsacramento.org; Jennifer Donlon Wyant, Mobility and Sustainability Division Manager, (916) 808-5913, jdonlonwyant@cityofsacramento.org; Department of Public Works

End

 

Presenter

Presenter: None

End

 

Attachments

Attachments:

1-Description/Analysis

2-Resolution

End

 

Description/Analysis

IssueDetail

Issue Detail: In 2022, the Federal Inflation Reduction Act (IRA) extended the Alternative Fuel Vehicle Refueling Property Credit (30C credit), which provides an income tax credit for qualified electric vehicle charging stations (also referred to as electric vehicle supply equipment or EVSE). Additionally, the IRA allowed tax-exempt entities, including local governments, to receive clean-energy related income tax credits as direct payments (“elective pay”) from the Internal Revenue Service (IRS).

 

In 2025, the One Big Beautiful Bill Act reduced tax credit eligibility and amended the 30C credit such that it will not be allowed for any property placed in service after June 30, 2026.

 

The City of Sacramento installed EVSE at four eligible sites in Fiscal Year 2026 through the Electric Vehicle (EV) Blueprint Phase II Project (C15210000). Staff recommend filing for elective pay to offset local project costs for the EV Blueprint Phase II Project.

 

The total direct construction cost for the seven stations at four EVSE sites was approximately $992,900. The City met the eligibility requirements to receive an elective payment equal to 6% of the total construction cost, or $59,574.

 

Staff submitted the required pre-registrations for the elective payments. In September 2026, the IRS approved the pre-registrations for these four eligible EVSE sites placed in service during Fiscal Year 2026.

 

This item authorizes formal submittal of the elective payment submissions to the IRS and provides administrative authority to accept and deposit the funds into the EV Blueprint Phase II Project (C15210000) budget.

End

 

PolicyConsiderations

Policy Considerations: The EV Blueprint Phase II Project supports the 2040 General Plan (Resolution No. 2024-0066) and Climate Action and Adaptation Plan (Resolution No. 2024-0067) policies to advance zero-emission vehicle (ZEV) technologies and is consistent with the City’s EV Strategy (Motion No. 2017-0374).

End

 

EconomicImpacts

Economic Impacts: None.

End

 

EnvironmentalConsiderations

Environmental Considerations: The request in this report is not a defined ‘project’ pursuant to environmental review consistent with the California Environmental Quality Act (CEQA). The request is an organizational or administrative activity that will not result in direct or indirect physical changes in the environment, as contemplated by Title 14, California Code of Regulations, Sections 15378(b)(5) and is, therefore, not subject to CEQA pursuant to CEQA Guidelines Section 15060(c)(3).

 

Applicable environmental review has already taken place as part of project construction activities.

End

 

Sustainability

Sustainability: Installation of EVSE supports the City's efforts to reduce greenhouse gas emissions from the transportation sector and improve local air quality.

End

 

Commission/Committee Action

Commission/Committee Action: None.

End

 

RationaleforRecommendation

Rationale for Recommendation: This action will provide funding to offset Measure U Funds from the Public Works Sustainability Program (I15220300) that were previously transferred to the EV Blueprint Phase II Project (C15210000) to pay for construction cost escalation. This action will enable a portion of these Measure U Funds to be transferred back to the Public Works Sustainability Program (I15220300) to further other sustainability efforts.

End

 

FinancialConsiderations

Financial Considerations: The EV Blueprint Phase II Project (C15210000) installed a total of 34 charging stations, with seven stations installed in the eligible Fiscal/Tax Year 2026 in census tracts that are eligible for elective pay. The total construction cost for these seven stations was $992,900 and was funded through a combination of state grant funds from the California Energy Commission, incentive funds from the Sacramento Metropolitan Air Quality Management District, rebates from the Sacramento Municipal Utility District, and local funds (Measure U).

 

These EVSE are eligible for a 6% elective payment from the IRS clean energy tax credit, totaling approximately $59,574. This elective payment will reimburse $59,574 of the $405,350 in local Measure U funds from the Public Works Sustainability Program that supported EVSE implementation. Filing for and accepting these funds will enable Measure U funds to be transferred back to the Public Works Sustainability Program (I15220300) to further other sustainability projects.