Title
[DISCUSSION] [Contract] 2026 Master Funding Agreement for Railyards Enhanced Infrastructure Financing District
End
FileID
File ID: 2026-01865
End
Location
Location: Downtown Railyards, District 4
End
Recommendation
Recommendation: Adopt a Resolution authorizing the City Manager or designee to execute a 2026 Master Funding Agreement for the Railyards Enhanced Infrastructure Financing District (“EIFD”) between Downtown Railyard Venture, LLC (“DRV”); Indomitable Ventures, LLC (“Indomitable”); the City of Sacramento Railyards Enhanced Infrastructure Financing District (the “Railyards EIFD”), a California governmental entity formed under California Government Code sections 53398.50 through 53398.88; and the City of Sacramento (the “City”), a California municipal corporation and charter city.
End
Contact
Contact: Marco Gonzalez, Senior Development Project Manager, (916) 808-5757, mgonzalez@cityofsacramento.org; Leslie Fritzsche, Interim Economic Development Director, (916) 808-5450, lfritzsche@cityofsacramento.org; Office of Innovation and Economic Development.
End
Presenter
Presenter: Marco Gonzalez, Senior Development Project Manager, (916) 808-5757, mgonzalez@cityofsacramento.org
End
Attachments
Attachments:
1-Description/Analysis
2-Resolution
3-2025 Master Funding Agreement
4-2026 Master Funding Agreement
End
Additional Description/Analysis
IssueDetail
Issue Detail: In recent years, the Sacramento Railyards has seen significant investments in infrastructure and new vertical development projects with the completion of the Wong Center (senior affordable housing), the AJ (mixed-use, mixed-income housing), the new Tani Cantil-Sakauye Sacramento County Courthouse, and the Kaiser hospital (now under construction). Despite this progress, the approximately 244-acre site in the heart of Sacramento’s central city requires additional investment to achieve the vision that was laid out in the Council-approved 2016 Railyards Specific Plan.
In November of 2024, the City Council unanimously approved the Sacramento Republic FC Term Sheet (Preliminary Term Sheet) that provided a framework to catalyze additional development in the Railyards including, but not limited to a Republic FC Soccer Stadium, rehabilitation of the Historic Central Shops district, and the City’s acquisition of two parcels that will be utilized to build out the Sacramento Valley Station (SVS) area consistent with the SVS Area Plan approved by Council in 2021. The development of these projects will generate millions of dollars worth of economic, cultural, and sports activity in the central city and will add new vitality to the City’s core.
On June 10th, 2025, the City Council unanimously approved execution of Definitive Documents for Implementation of the Term Sheet as well as expansion of the existing Sacramento Railyards Stadium Enhanced Infrastructure Financing District and Infrastructure Financing Plan (IFP). The 2025 Master Funding Agreement (Attachment 3) was part of the Definitive Documents approved by City Council.
On July 22, 2025, the Railyards Public Finance Authority terminated and abandoned the Railyards EIFD expansion process after a protest which was consistent with EIFD statute. Flowing from that, the 2025 Master Funding Agreement was also not executed by the EIFD.
Like the 2025 Master Funding Agreement, the 2026 Master Funding Agreement (“2026 MFA”) will provide for a financing structure through which Indomitable, DRV, and the City may be reimbursed with tax increment revenues for their eligible costs related to the costs of the construction of the public facilities in the IFP. The construction of the public facilities in the IFP is necessary to support further development within the Railyards.
The attached resolution (Attachment 2) authorizes the City Manager to execute the 2026 MFA (Attachment 4) with the aim of aligning it with the IFP being brought for Council approval on November 10th, 2026 in the distribution of tax increment and other related matters. The IFP being brought to City Council concurrent with the 2026 MFA has different boundaries from the one brought forward in 2025 and increases the residual tax increment pledged to fund affordable housing from 20% to 25% (discussed further below). Other than this one significant change, all other revisions to the 2026 MFA as compared to the 2025 agreement are of a minor or technical nature.
Like the 2025 agreement, the 2026 MFA (1) describes and defines the costs of each of the parties that are eligible for reimbursement from tax increment revenues generated from property within the EIFD (as described in additional detail below), (2) delineates the parameters for a potential CFD that would be formed by the City within the EIFD’s East Project Area to be used to finance the construction of Indomitable’s eligible facilities, (3) provides for waterfalls that determine how the property tax increment generated within the EIFD’s East and West Project Areas will be disbursed, (4) provides parameters for future EIFD bonds including how the proceeds of such bonds will be spent, and (5) provides for inflation adjustments for DRV’s and Indomitable’s eligible costs for a limited period so long as the construction of Music Venue Project and/or Stadium do not fall behind schedule.
Indomitable will be reimbursed for its costs for the design and construction of the infrastructure required to construct and operate the Stadium, currently estimated at $45 million, DRV will be reimbursed for up to $50 million of its costs incurred for the design and construction of the public facilities within the IFP, and the City will receive $14 million for its costs related primarily to the land acquisitions needed to build out the Sacramento Valley Station. Indomitable and DRV’s costs described above will receive inflation adjustment for a limited period so long as the construction of the Music Venue Project and/or Stadium do not fall behind schedule. All of the infrastructure that DRV and Indomitable are required to construct and the City’s land acquisitions needed to build out the Sacramento Valley Station are eligible public facilities included in the EIFD’s IFP. The reimbursements to the City, DRV and Indomitable will be made only from the net-new incremental property tax revenue that derived from taxable property within the EIFD.
After the satisfaction of the City’s, Indomitable’s and DRV’s eligible costs, any additional tax increment will flow to the EIFD with 25% of the residual tax increment pledged exclusively for the construction of affordable housing.
EIFD reimbursements will only be made for the eligible facilities included in the EIFD’s IFP. No EIFD reimbursements will be provided for the Stadium-site construction work. The EIFD has no additional financial obligations to Indomitable and DRV if incremental property tax revenue generated within the EIFD’s boundaries is inadequate to cover the reimbursements to Indomitable or DRV.
A companion report on the Council Agenda (Report # 2026-01236- Approval of the Expansion of the City of Sacramento Railyards Enhanced Infrastructure Financing District and the Amended Infrastructure Financing Plan, including the Division of Taxes Set Forth Therin, and Authorizing Other Related Actions), includes a resolution for: 1) amending the Infrastructure Financing Plan; and 2) approving the expansion of the City of Sacramento Railyards EIFD.
End
PolicyConsiderations
Policy Considerations: Approval of the 2026 MFA is a necessary step to provide for the financing of the public infrastructure and other projects of communitywide significance identified in the EIFD’s IFP and necessary for redevelopment of the Railyards. The 2026 MFA also provides that 25% of the residual tax increment revenues will be dedicated to affordable housing.
End
EconomicImpacts
Economic Impacts: The redevelopment of the Railyards will generate significant economic benefits to the community, the City, and the region. Highlights of its impact include the creation of 13,539 direct jobs, $2.11 billion in annual wages across Sacramento County and over $4.44 billion in economic output.
End
EnvironmentalConsiderations
Environmental Considerations: California Environmental Quality Act (CEQA): California Environmental Quality Act (CEQA):
The action involves approving a potential financing mechanisms for improvements associated with the Railyards Development project. The action is not considered a project under CEQA. The action involves review and discussion of the creation of a government funding mechanism or other government fiscal activities, which do not involve any approval or commitment to any specific project which may result in a potentially significant physical impact on the environment. CEQA Guidelines section 15352. CEQA Guidelines section 15378(b) (4) & (5); 15060(c)(3). To the extent any planned infrastructure funded by the financing mechanism will result in physical changes to the environment, those changes have been studied in the Railyards Specific Plan Environmental Impact Report SCH No. 2006032058 (Resolution # 2007-903), the Railyards Specific Plan Update, Kaiser Permanente Medical Center and Stadium Subsequent Environmental Impact Report (Resolution #2016-0379) and Addendum. None of the circumstances set forth in Public Resources Code section 21166 and Guidelines sections 15162 require additional environmental review. The affordable housing component of the EIFD is only a funding mechanism at this point and therefore exempt from environmental review pursuant to CEQA Guidelines section 15378(b) (4), 15060(c)(3). When a specific affordable housing project is identified and proposed, it will be reviewed for CEQA compliance. The creation of the funding mechanism does not commit the City to any particular affordable housing project or require its construction.
End
Sustainability
Sustainability: Not applicable.
End
Commission/Committee Action
Commission/Committee Action: None.
End
RationaleforRecommendation
Rationale for Recommendation: The approval of the 2026 MFA formalizes the financial obligations of the parties as outlined in the Definitive Documents approved by Council on June 10th, 2025 and provides the method by which the redevelopment of the Railyards will be financed. The 2026 MFA provides that, after each of the parties is fully reimbursed, 25% of the residual tax increment will be pledged exclusively to the construction of affordable housing.
End
FinancialConsiderations
Financial Considerations: The 2026 MFA provides that the tax increment revenues generated from taxable property within the boundaries of the Railyards EIFD will be used to reimburse the City, DRV and Indomitable for their eligible costs related to the construction of the public facilities and land acquisitions included in the IFP, to pay debt service on municipal bonds, notes, or other debt obligations issued to finance such eligible costs, or all or some of the foregoing. Indomitable’s eligible costs are estimated at $45 million, DRV’s eligible costs are $50 million, and the City’s eligible costs are $14 million. Indomitable’s and DRV’s eligible costs may be increased by an inflation adjuster for a limited period so long as the construction of the Music Venue Project and/or Stadium do not fall behind schedule.
The 2026 MFA provides that, upon the satisfaction of each of the parties’ eligible costs, 25% of the residual tax increment will be pledged exclusively to the construction of affordable housing.
The IFP contains a limit of $825 million in incremental property taxes over the life of the Railyards EIFD that the City may allocate to the Railyards EIFD and provides that such allocations will end no later than 2076. The City has no obligation to contribute any revenues to the Railyards EIFD other than the tax increment revenues and only to the extent of the limits in the IFP and caps established in the 2026 MFA.
End
LocalBusinessEnterprise
Local Business Enterprise (LBE): Not applicable.
End