Title
[Contract Awards and Supplements] Plans and Specifications Approval, Budgetary Adjustments, Contract Supplement and Contract Award for the Lampasas Avenue & Rio Linda Boulevard Project (T15205500) [Published for 10-day Review 10/29/2026]
End
FileID
File ID: 2026-01704
End
Location
Location: The intersection of Lampasas Avenue and Rio Linda Boulevard, District 2
End
Recommendation
Recommendation: Adopt a Resolution: 1) approving the Plans and Specifications for the Lampasas Avenue & Rio Linda Boulevard Project (T15205500); 2) authorizing the City Manager or designee to increase the revenue and expenditure budgets of the Lampasas Avenue & Rio Linda Boulevard Project (T15205500) by $2,076,220 (Other Capital Grants, Fund 3703); 3) authorizing the City Manager or designee to increase the expenditure budget of the Lampasas Avenue & Rio Linda Boulevard Project (T15205500) by $667,000 (Major Street Construction Fund, Fund 2007); 4) awarding the construction contract for the Lampasas Avenue & Rio Linda Boulevard Project (T15205500) to Ghilotti Bros, Inc. for an amount not to exceed $1,698,799; 5) authorizing the City Manager or designee to execute the construction contract for the Lampasas Avenue & Rio Linda Boulevard Project (T15205500) with Ghilotti Bros, Inc. for an amount not to exceed $1,698,799; 6) authorizing the City Manager or designee to execute Supplemental Agreement No. 6 to City Agreement No. 2021-1207 with Kimley-Horn and Associates, Inc. for an amount not-to-exceed $60,359, for a new contract not-to-exceed amount of $258,701; 7) resetting the City Manager administrative authority to issue supplemental agreements with Kimley-Horn and Associates, Inc. for City Agreement No. 2021-1207; 8) awarding a Professional Services Agreement for an amount not-to-exceed $342,066 with Salaber Associates, Inc. for the Lampasas Avenue & Rio Linda Boulevard Project (T15205500); 9) authorizing the City Manager or designee to execute a Professional Services Agreement for an amount not-to-exceed $342,066 with Salaber Associates, Inc. for the Lampasas Avenue & Rio Linda Boulevard Project (T15205500); 10) awarding a Professional Services Agreement for an amount not-to-exceed $330,243 with Salaber Associates, Inc. for the La Mancha Way / Valley Hi Drive Corridor Improvements Project (T15205300); and 11) authorizing the City Manager or designee to execute a Professional Services Agreement for an amount not-to-exceed $330,243 with Salaber Associates, Inc. for the La Mancha Way / Valley Hi Drive Corridor Improvements Project (T15205300).
End
Contact
Contact: James Kragh, Associate Engineer, (916) 808-6842, jmkragh@cityofsacramento.org; William Shunk, Senior Engineer, (916) 808-2986, wshunk@cityofsacramento.org; Ofelia Avalos, Engineering Manager, (916) 808-5054, oavalos@cityofsacramento.org; Department of Public Works
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Resolution
3-Project Plans for the Lampasas Avenue & Rio Linda Boulevard Project (T15205500)
4-Construction Contract for the Lampasas Avenue & Rio Linda Boulevard Project (T15205500)
5-Supplemental Agreement for the Lampasas Avenue & Rio Linda Boulevard Project (T15205500)
6-Construction Management Contract for the Lampasas Avenue & Rio Linda Boulevard Project (T15205500)
7-Construction Management Contract for the La Mancha Way / Valley Hi Drive Corridor Improvements Project (T15205300)
End
Description/Analysis
IssueDetail
Issue Detail: The Highway Safety Improvement Program (HSIP)-9 Lampasas Avenue and Rio Linda Boulevard Intersection Safety Project is an operational improvement that will enhance safety at the Lampasas Avenue and Rio Linda Boulevard intersection.
This project includes the installation of pedestrian crossings on both approaches of Lampasas Avenue and on the north approach of Rio Linda Boulevard at the intersection. Pedestrian refuge islands will be constructed on the north approach to reduce pedestrian exposure while crossing. The intersection will also be restriped and realigned to reduce excess pavement and improve the clarity and efficiency of vehicle turning movements.
In addition, the eastbound approach of Lampasas Avenue will be modified to function as an exit-only movement from the intersection, reducing vehicle conflict points and improving overall intersection safety.
The project was selected for funding in Cycle 9 of the Highway Safety Improvement Program (HSIP) based on the frequency of crashes resulting in injuries and fatalities at the intersection. Additional funding for the project was secured in the Sacramento Area Council of Governments (SACOG) 2020 Regional program for the for-project elements that were not eligible for HSIP reimbursement. Appropriation of HSIP and SACOG construction funding is necessary to construct the project.
The project plans and specifications have been completed and are included as Attachment 3.
The project was advertised for construction and received nine bids. Staff recommend awarding the construction contract to the lowest responsive and responsible bidder, Ghilotti Bros, Inc.
The City advertised a competitive solicitation for proposals from engineering consulting firms to provide construction management and inspection services for both the Lampasas Avenue & Rio Linda Boulevard Project (T15205500) and for the La Mancha Way / Valley Hi Drive Corridor Improvements Project (T15205300). Three firms submitted proposals, and a panel comprised of staff from the Department of Public Works recommended selection of the top ranked firm, Salaber Associates, Inc. Selection of an experienced and qualified construction management firm is necessary to ensure the project is appropriately staffed for construction oversight which is anticipated to start following the construction contract award.
Kimley-Horn and Associates, Inc. was awarded a professional services agreement (City Agreement No. 2021-1207) to perform final design services on October 27, 2021. Approval of the execution of Supplemental No. 6 and resetting the City Manager’s authority to issues supplemental agreements to City Agreement No. 2021-1207 will allow for efficient accommodation of design support needs during construction.
End
PolicyConsiderations
Policy Considerations: The actions requested herein are consistent with the City General Plan goals and key policies that accommodate and promote safe and convenient travel for all users. The project will prioritize pedestrian mobility (M 1.2); increase bicycling and walking (M-1.11); improve walking connectivity (M-1.15); and enhance walking safety (M-1.19).
The Sacramento City Code Section 4.04.020 and the City Council Rules of Procedure (Chapter 7, Section E.2.d) mandate that unless waived by a 2/3 vote of the City Council, all labor agreements, and all agreements greater than $1,000,000 shall be made available to the public at least ten (10) days prior to City Council action. This item was published for 10-day review on October 29, 2026, in compliance with the City Code.
End
EconomicImpacts
Economic Impacts: This new infrastructure is expected to create 6.8 total jobs (3.91 direct jobs and 2.89 jobs through indirect and induced actives) and create $1,048,897.65 in total economic output ($661,128.21 of direct output and another $387,769.44 of output through indirect and induced activities). The indicated economic impacts are estimates calculated using a calculation tool developed by the Center for Strategic Economic Research (CSER). CSER utilized the IMPLAN input-output model (2009 coefficients) to quantify the economic impacts of a hypothetical $1 million of spending in various construction categories within the City of Sacramento in an average one-year period. Actual impacts could differ significantly from the estimates and neither the City of Sacramento nor CSER shall be held responsible for consequences resulting from such differences.
End
EnvironmentalConsiderations
Environmental Considerations:
California Environmental Quality Act (CEQA): The City of Sacramento Environmental Planning Services has reviewed this project and determined that it is exempt from the provisions of CEQA under Section 15301(c).
National Environmental Policy Act (NEPA): The project has been determined to be categorically excluded from National Environmental Policy Act (NEPA) review under Sections 23 USC 326 and 23 CFR 771 (c).
End
Sustainability
Sustainability: The project is consistent with the City’s General Plan goals to help improve the health of residents by promoting walking and bicycling, and to create a healthier urban environment by eliminating pedestrian barriers with the construction of safe pedestrian crossings. The project will reduce dependence on the private automobile, decrease the use of fossil fuels, and encourage active modes of transportation.
End
Commission/Committee Action
Commission/Committee Action: The project was presented as an informational item at the August 2024 meeting of the Sacramento Disabilities Advisory Commission and the November 2024 meeting of the Sacramento Active Transportation Commission.
End
RationaleforRecommendation
Rationale for Recommendation:
The City Council action is required to perform the budgetary adjustments necessary to award and complete construction of the Lampasas Avenue & Rio Linda Boulevard Project (T15205500), which includes appropriation of $2,076,220 in HSIP construction funding.
The project was advertised for construction with an engineer’s estimate of $2,325,210. A total of nine bids were received on August 5, 2026, as summarized below:
|
Contractor |
Bid |
|
Ghilotti Bros, Inc. |
$1,698,798.50 |
|
Ghilotti Construction Company, Inc. |
$1,737,018.50 |
|
FBD Vanguard Construction |
$1,824,455.00 |
|
Dutch Contracting, Inc |
$1,839,991.84 |
|
Granite Rock Company |
$1,852,004.90 |
|
Martin Brothers Construction |
$1,987,853.00 |
|
McGuire and Hester |
$2,052,960.00 |
|
Martin General Engineering |
$2,061,424.25 |
|
Lund Construction |
$2,102,237.60 |
All bidders met the required bid conditions. Staff recommend that the construction contract be awarded to the lowest responsive and responsible bidder, Ghilotti Bros, Inc. Construction is anticipated to begin November 2026 and be completed by June 2027.
A request for proposals (RFP) was advertised on May 2, 2025, for professional services to provide construction management, inspection, materials testing, and construction staking for two similar projects: the Lampasas Avenue & Rio Linda Boulevard Project (T15205500) and the La Mancha Way / Valley Hi Drive Corridor Improvements Project (T15205300). The City received proposals from three teams: 3D Built, UNICO Engineering, Inc., and Salaber Associates, Inc. Based upon the merits of the written proposals and interviews of the consultant teams, a panel representing staff from the Departments of Public Works reviewed and recommended Salaber Associates, Inc. as the top-ranked consultant team. Approval by the City Council is needed to award the Professional Services Agreement with Salaber Associates, Inc.
Approval by the City Council is needed to execute Supplemental Agreement No. 6 and reset the administrative authority for contract amendments to City Agreement No. 2021-1207 with Kimley-Horn and Associates, Inc. to allow design support services to be provided during construction.
End
FinancialConsiderations
Financial Considerations: The estimated total cost to complete construction and construction management activities for the Lampasas Avenue & Rio Linda Boulevard Project (T15205500) is approximately $2,140,000. By approving the budgetary adjustments for $2,076,220 (Other Capital Grants, Fund 3703) and $667,000 (Major Street Construction Fund, Fund 2007) to the revenue and expenditure budgets of the Lampasas Avenue & Rio Linda Boulevard Project (T15205500), there will be sufficient funding to award the construction contract to Ghilotti Bros, Inc. for an amount not-to-exceed $1,698,798.50, execute Supplemental Agreement No. 6 to City Agreement No. 2021-1207 with Kimley-Horn and Associates, Inc. for an amount not-to-exceed $60,358.91, and award a professional services agreement for construction management services to Salaber Associates, Inc. for an amount not-to-exceed $342,065.32 to complete the project.
The estimated total cost to complete construction and construction management activities for the La Mancha Way / Valley Hi Drive Corridor Improvements Project (T15205300) is approximately $1,890,400. City Council voted to adopt a resolution that will increase the expenditure budget for the La Mancha Way / Valley Hi Drive Corridor Improvements Project (T15205300) by $2,981,000 on September 29, 2026. With that budgetary adjustment, there issufficient funding to award the professional services agreement for construction management services to Salaber Associates, Inc. for an amount not-to-exceed $330,242.15 to complete the project.
No General Funds are planned or allocated to either project.
End
LocalBusinessEnterprise
Local Business Enterprise (LBE): The City’s LBE requirement for this project is not applicable due to federal funding requirements.