Legislation Details

File #: 2026-01951    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 10/21/2026 In control: City Council - 5PM
On agenda: 12/1/2026 Final action:
Title: [Contract Amendment] Change Order: Pioneer Structural Repairs
Attachments: 1. 2026-01951 STAFF REPORT
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

[Contract Amendment] Change Order: Pioneer Structural Repairs

End

 

FileID

File ID: 2026-01951

End

 

Location

Location: Citywide

End

 

Recommendation

Recommendation: Pass a Motion: 1) authorizing the City Manager or designee to execute Change Order No. 4 to City Agreement No. 2025-0803 with NMI Industrial Holdings, LLC, for an amount not to exceed $126,078, bringing the agreement’s total not-to-exceed amount to $1,690,799; and 2) resetting the City Manager or designee’s authority to issue Change Orders for the Agreement. 

End

 

Contact

Contact: Tim Moresco, Project Manager (916) 808-1432, tmoresco@cityofsacramento.org; Michelle Carrey, Engineering & Water Resources Division Manager, (916) 808-1438, mcarrey@cityofsacramento.org; Dalia Fadl, Director, (916) 808-3765, dfadl@cityofsacramento.org; Department of Utilities

End

 

Presenter

Presenter: None

End

 

Attachments

Attachments:

1-Description/Analysis

2-Change Order

End

 

Description/Analysis

IssueDetail

Issue Detail: Staff recommend City Council approve Change Order No. 4 to City Agreement No. 2025-0803 with NMI Industrial Holdings, LLC to cover additional costs associated with the increase in concrete repair at Pioneer Reservoir due to the need to address the spalled concrete. The project plans identified several locations that needed concrete spalling repair on the exterior of the structure, and as the repairs were being performed, a much larger concrete spalling area was identified that required a large increase in square footage to the repair.  The additional deterioration was not incorporated into the original project scope, because it was not visible during the inspections and condition assessments completed during the planning and design phases of the project.

End

 

PolicyConsiderations

Policy Considerations: This Change Order exceeds the City Manager’s approval authority and requires Council approval per City Code 3.04.020. 

End

 

EconomicImpacts

Economic Impacts: This Change Order is expected to create 0.48 total jobs (0.28 direct jobs and 0.2 jobs through indirect and induced activities) and create $74,140.15 in total economic output ($46,731.10 of direct output and another $27,409.05 of output through indirect and induced activities).

 

The indicated economic impacts are estimates calculated using a calculation tool developed by the Center for Strategic Economic Research (CSER).  CSER utilized the IMPLAN input-output model (2009 coefficients) to quantify the economic impacts of a hypothetical $1 million of spending in various construction categories within the City of Sacramento in an average one-year period.  Actual impacts could differ significantly from the estimates and neither the City of Sacramento nor CSER shall be held responsible for consequences resulting from such differences.

End

 

EnvironmentalConsiderations

Environmental Considerations: The subject projects were reviewed and determined to be categorically exempt from the California Environmental Quality Act (CEQA). The projects include performing restoration or rehabilitation of deteriorated or damaged structures to meet current standards of public health and safety (CEQA Guidelines Section 15301 (d)).

End

 

Sustainability

Sustainability: The proposed project is consistent with the 2040 General Plan goal PFS-3.6, “Combined Sewer System Rehabilitation and Improvements” as it aims to rehabilitate aging Combined Sewer System (CSS) facilities to continue to decrease flooding, CSS outflows or combined sewer overflows.

End

 

Commission/Committee Action

Commission/Committee Action: Not applicable.

End

 

RationaleforRecommendation

Rationale for Recommendation: Change Order No. 4 is necessary to compensate the contractor for additional work required to address unforeseen field conditions and owner-directed improvements. These changes enhance worker safety, protect structural integrity, and improve the operational reliability of the Pioneer Reservoir, ensuring the project meets its intended goals for public health, safety, and infrastructure performance.

End

 

FinancialConsiderations

Financial Considerations: The original not-to-exceed amount of the contract was $1,215,200.  Change Orders No. 1 through 3 increased the contract amount by $349,521 to a not-to-exceed amount of $1,564,721. Proposed Change Order No. 4 in the amount of $126,078 would increase the contract not-to-exceed amount to $1,690,799. There are sufficient funds in the CSS Sump/Treatment Facilities Program (X14170500, Funds 6006 and 6021) to execute this Change Order.  

 

There are no General Funds allocated or planned for this project.

End

 

LocalBusinessEnterprise

Local Business Enterprise (LBE): NMI Industrial Holdings LLC is an LBE.

End

 

Background

In August 2023, JDH Corrosion Consultants, Inc and Brown and Caldwell teamed up and performed a condition assessment of the interior and exterior of Pioneer Reservoir.  In this condition assessment, several locations were identified to be suffering from concrete cracks and spalling, compromising the structural integrity of the structure.  Brown and Caldwell later used these findings when performing a Business Case Evaluation (BCE), which is a structured process used for assessing feasibility, viability, and potential impacts of several different alternative solutions. This project was identified from the BCE as a necessary project to perform to continue to extend the life of the facility and provide the City with enough time to plan and budget for some of the other long-term alternatives.

 

On July 22, 2025, the construction contract 2025-0803 was awarded to NMI Industrial Holdings, LLC in the amount of $1,215,200. The notice to proceed with construction activities was provided to the Contractor on August 12, 2025.  Within the first few weeks of the contract, it was determined that the anticipated lead time for the material needed for the project would take 10 to 12 weeks, which would put the project work into November, which is considered in the wet weather season.  It was anticipated that once the material was received, it would take roughly 6 weeks to perform the work within Pioneer Reservoir.  The City did not want to take the risk of having Pioneer Reservoir offline for that duration during the wet weather months and therefore suspended the project until June 2, 2026.

 

This project has had four (4) Contract Change Orders to date. The table below summarizes the contract change orders to date:

 

 

Item

Change Order Amount

Contract Value

Original Value

$             0

$ 1,215,200.00

CCO #1

$  310,758

$ 1,525,958

CCO #2

$    29,510

$ 1,555,468

CCO #3

$      9,253

$ 1,564,721

CCO #4

$  126,078

$ 1,690,799

 

Change Order No. 1 was issued to cover additional costs associated with cleaning the reservoir basins to ensure worker safety, performing ground-penetrating radar (GPR) scanning to locate reinforcing steel prior to drilling into concrete surfaces, addressing material cost escalation resulting from the project suspension, and fabricating and installing a 60-inch sluice gate in Basin 1 to improve operational reliability. The sluice gate is anticipated to be delivered in February 2027 and installed in May or June 2027. This change order was approved by the City Council on April 14, 2026.

 

Change Order No. 2 was issued to account for increased labor costs resulting from the project suspension between August 2025 and June 2026. This change order was fully executed on July 6, 2026.

 

Change Order No. 3 was issued to cover the additional steel required to enlarge the base plates for the new steel columns, allowing the anchor bolt holes to avoid existing reinforcing steel in the concrete floor. The change order also included credit for eliminating the removal of the existing steel columns prior to installation of the new columns due to safety concerns, as well as compensation for additional preparation work associated with relocating three steel columns from their original design locations to new locations. This change order was fully executed on August 14, 2026.

End