Title
[Contract Amendment] Change Order: Pioneer Structural Repairs
End
FileID
File ID: 2026-01951
End
Location
Location: Citywide
End
Recommendation
Recommendation: Pass a Motion: 1) authorizing the City Manager or designee to execute Change Order No. 4 to City Agreement No. 2025-0803 with NMI Industrial Holdings, LLC, for an amount not to exceed $126,078, bringing the agreement’s total not-to-exceed amount to $1,690,799; and 2) resetting the City Manager or designee’s authority to issue Change Orders for the Agreement.
End
Contact
Contact: Tim Moresco, Project Manager (916) 808-1432, tmoresco@cityofsacramento.org; Michelle Carrey, Engineering & Water Resources Division Manager, (916) 808-1438, mcarrey@cityofsacramento.org; Dalia Fadl, Director, (916) 808-3765, dfadl@cityofsacramento.org; Department of Utilities
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Change Order
End
Description/Analysis
IssueDetail
Issue Detail: Staff recommend City Council approve Change Order No. 4 to City Agreement No. 2025-0803 with NMI Industrial Holdings, LLC to cover additional costs associated with the increase in concrete repair at Pioneer Reservoir due to the need to address the spalled concrete. The project plans identified several locations that needed concrete spalling repair on the exterior of the structure, and as the repairs were being performed, a much larger concrete spalling area was identified that required a large increase in square footage to the repair. The additional deterioration was not incorporated into the original project scope, because it was not visible during the inspections and condition assessments completed during the planning and design phases of the project.
End
PolicyConsiderations
Policy Considerations: This Change Order exceeds the City Manager’s approval authority and requires Council approval per City Code 3.04.020.
End
EconomicImpacts
Economic Impacts: This Change Order is expected to create 0.48 total jobs (0.28 direct jobs and 0.2 jobs through indirect and induced activities) and create $74,140.15 in total economic output ($46,731.10 of direct output and another $27,409.05 of output through indirect and induced activities).
The indicated economic impacts are estimates calculated using a calculation tool developed by the Center for Strategic Economic Research (CSER). CSER utilized the IMPLAN input-output model (2009 coefficients) to quantify the economic impacts of a hypothetical $1 million of spending in various construction categories within the City of Sacramento in an average one-year period. Actual impacts could differ significantly from the estimates and neither the City of Sacramento nor CSER shall be held responsible for consequences resulting from such differences.
End
EnvironmentalConsiderations
Environmental Considerations: The subject projects were reviewed and determined to be categorically exempt from the California Environmental Quality Act (CEQA). The projects include performing restoration or rehabilitation of deteriorated or damaged structures to meet current standards of public health and safety (CEQA Guidelines Section 15301 (d)).
End
Sustainability
Sustainability: The proposed project is consistent with the 2040 General Plan goal PFS-3.6, “Combined Sewer System Rehabilitation and Improvements” as it aims to rehabilitate aging Combined Sewer System (CSS) facilities to continue to decrease flooding, CSS outflows or combined sewer overflows.
End
Commission/Committee Action
Commission/Committee Action: Not applicable.
End
RationaleforRecommendation
Rationale for Recommendation: Change Order No. 4 is necessary to compensate the contractor for additional work required to address unforeseen field conditions and owner-directed improvements. These changes enhance worker safety, protect structural integrity, and improve the operational reliability of the Pioneer Reservoir, ensuring the project meets its intended goals for public health, safety, and infrastructure performance.
End
FinancialConsiderations
Financial Considerations: The original not-to-exceed amount of the contract was $1,215,200. Change Orders No. 1 through 3 increased the contract amount by $349,521 to a not-to-exceed amount of $1,564,721. Proposed Change Order No. 4 in the amount of $126,078 would increase the contract not-to-exceed amount to $1,690,799. There are sufficient funds in the CSS Sump/Treatment Facilities Program (X14170500, Funds 6006 and 6021) to execute this Change Order.
There are no General Funds allocated or planned for this project.
End
LocalBusinessEnterprise
Local Business Enterprise (LBE): NMI Industrial Holdings LLC is an LBE.
End
Background
In August 2023, JDH Corrosion Consultants, Inc and Brown and Caldwell teamed up and performed a condition assessment of the interior and exterior of Pioneer Reservoir. In this condition assessment, several locations were identified to be suffering from concrete cracks and spalling, compromising the structural integrity of the structure. Brown and Caldwell later used these findings when performing a Business Case Evaluation (BCE), which is a structured process used for assessing feasibility, viability, and potential impacts of several different alternative solutions. This project was identified from the BCE as a necessary project to perform to continue to extend the life of the facility and provide the City with enough time to plan and budget for some of the other long-term alternatives.
On July 22, 2025, the construction contract 2025-0803 was awarded to NMI Industrial Holdings, LLC in the amount of $1,215,200. The notice to proceed with construction activities was provided to the Contractor on August 12, 2025. Within the first few weeks of the contract, it was determined that the anticipated lead time for the material needed for the project would take 10 to 12 weeks, which would put the project work into November, which is considered in the wet weather season. It was anticipated that once the material was received, it would take roughly 6 weeks to perform the work within Pioneer Reservoir. The City did not want to take the risk of having Pioneer Reservoir offline for that duration during the wet weather months and therefore suspended the project until June 2, 2026.
This project has had four (4) Contract Change Orders to date. The table below summarizes the contract change orders to date:
|
Item |
Change Order Amount |
Contract Value |
|
Original Value |
$ 0 |
$ 1,215,200.00 |
|
CCO #1 |
$ 310,758 |
$ 1,525,958 |
|
CCO #2 |
$ 29,510 |
$ 1,555,468 |
|
CCO #3 |
$ 9,253 |
$ 1,564,721 |
|
CCO #4 |
$ 126,078 |
$ 1,690,799 |
Change Order No. 1 was issued to cover additional costs associated with cleaning the reservoir basins to ensure worker safety, performing ground-penetrating radar (GPR) scanning to locate reinforcing steel prior to drilling into concrete surfaces, addressing material cost escalation resulting from the project suspension, and fabricating and installing a 60-inch sluice gate in Basin 1 to improve operational reliability. The sluice gate is anticipated to be delivered in February 2027 and installed in May or June 2027. This change order was approved by the City Council on April 14, 2026.
Change Order No. 2 was issued to account for increased labor costs resulting from the project suspension between August 2025 and June 2026. This change order was fully executed on July 6, 2026.
Change Order No. 3 was issued to cover the additional steel required to enlarge the base plates for the new steel columns, allowing the anchor bolt holes to avoid existing reinforcing steel in the concrete floor. The change order also included credit for eliminating the removal of the existing steel columns prior to installation of the new columns due to safety concerns, as well as compensation for additional preparation work associated with relocating three steel columns from their original design locations to new locations. This change order was fully executed on August 14, 2026.
End