Title
[Contract] Kinney Police Facility HVAC System Improvements (C13001900) [Published for 10-Day Review 10/29/2026]
End
FileID
File ID: 2026-01876
End
Location
Location: 3550 Marysville Boulevard, District 2
End
Recommendation
Recommendation: Adopt a Resolution: 1) authorizing the City Manager or designee to increase the revenue and expenditure budget of the Energy Reinvestment Program (C13001900) by $493,300 (Federal Capital Grants, Fund 3703); 2) authorizing the City Manager or designee to transfer $440,000 (General Fund, Fund 1001) from the expenditure budget of the City Facility Reinvest Program (C13900000) to the expenditure budget of the Energy Reinvestment Program (C13001900); 3) awarding a construction contract to Mesa Energy Systems, Inc. in an amount not-to-exceed $1,098,325 for Kinney Police Facility Heating, Ventilation and Air Conditioning (HVAC) System Improvements; and 4) authorizing the City Manager or designee to execute the contract specified above.
End
Contact
Contact: Nadia Melgoza, Senior Architect, (916) 808-2262, nmelgoza@cityofsacramento.org; Mark C. Brown, Supervising Engineer, (916) 808-7118, mcbrown@cityofsacramento.org; James Christensen, Facilities Manager, (916) 808-5863, jechristensen@cityofsacramento.org; Department of Public Works
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Contract - Mesa Energy Systems, Inc.
3-Resolution
End
Description/Analysis
IssueDetail
Issue Detail: The Facilities & Real Property Management Division (Facilities) secured an Energy Efficiency and Conservation Block Grant (EECBG) to modernize the HVAC system at the Kinney Police Facility. This grant is specifically designed to support projects that replace outdated mechanical systems with advanced, energy-efficient equipment and controls. Only the direct costs of replacing old equipment with new, efficient models are eligible for funding.
The Kinney Police Facility was selected for this initiative because its HVAC system had reached the end of its operational life and was no longer reliable. The project will utilize $493,000 in grant funds to replace all major mechanical components, including:
• Two primary rooftop air handling units
• Hot water boiler
• Exhaust fans
• Zone terminal units
• Controls
Each of these components has exceeded its useful life. Facilities calls for failed performance and on-going costs for component replacement are increasing. The new installations will be modern equivalents, surpassing previous energy-efficiency standards. As a result, the Kinney Police Facility will benefit from reduced energy bills and fewer maintenance calls, ensuring both cost savings and improved reliability.
End
PolicyConsiderations
Policy Considerations: The recommendations in this report are in accordance with the provisions of City Code Chapter 3.56 which requires City Council approval of contracts of $250,000 or more.
The Sacramento City Code Section 4.04.020 and the City Council Rules of Procedure (Chapter 7, Section E.2.d) which require that unless waived by 2/3 vote of the of the City Council, all labor agreements, and all agreements greater than $1,000,000 shall be made available to the public at least ten (10) days prior to City Council Action. This item was published for 10-day review on October 29, 2026, in compliance with the City Code.
End
EconomicImpacts
Economic Impacts: The recommended contract is expected to create 8.13 total jobs (5.16 direct jobs and 2.97 jobs through indirect and induced actives) and create $1,072,539 in total economic output ($687,525 of direct output and another $385,014 of output through indirect and induced activities).
The indicated economic impacts are estimates calculated using a calculation tool developed by the Center for Strategic Economic Research (CSER). CSER utilized the IMPLAN input-output model (2009 coefficients) to quantify the economic impacts of a hypothetical $1 million of spending in various construction categories within the City of Sacramento in an average one-year period. Actual impacts could differ significantly from the estimates and neither the City of Sacramento nor CSER shall be held responsible for consequences resulting from such differences.
End
EnvironmentalConsiderations
Environmental Considerations: The action is exempt from review under the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15302. The action consists of the replacement or reconstruction of existing structures and facilities where the new structure will be located on the same site as the replaced structure and will have substantially the same purpose and capacity as the structure replaced. The action involves replacement or reconstruction of existing improvements and/or facilities involving negligible or no expansion of capacity.
End
Sustainability
Sustainability: Not applicable.
End
Commission/Committee Action
Commission/Committee Action: Not applicable.
End
RationaleforRecommendation
Rationale for Recommendation: On July 21, 2026, the Department of Public Works Facilities and Real Property Management Division issued Invitation for Bid (IFB) No. B26014541003 for Kinney Police Facility HVAC Improvements. Three bids were received. Mesa Energy Systems, Inc. was determined to be the lowest responsive and responsible bidder. The results of IFB No. B26014541003 are listed in the table below.
|
Contractor |
Bid Amount |
Responsive |
|
Mesa Energy Systems, Inc. |
$1,098,325 |
Yes |
|
Acco Engineered Systems, Inc. |
$1,299,169 |
Yes |
|
Lawson SSP Group LLC |
$1,351,300 |
Yes |
Construction is anticipated to begin in Fall of 2026. City staff recommend entering into a contract with Mesa Energy Systems, Inc. in the amount of $1,098,325.
End
FinancialConsiderations
Financial Considerations: The estimate cost to complete construction and construction management activities for Energy Reinvestment Program (C13001900) is approximately $1,450,000. By approving the budgetary adjustments of $493,300 (Federal Capital Grant, Fund 3703) and the transfer of $440,000 (General Fund, Fund 1001) from the expenditure budget of the City Facility Reinvest Program (C13900000) to the expenditure budget of the Energy Reinvestment Program (C13001900), there will be sufficient funding to award the contract to Mesa Energy Systems, Inc., for the Kinney Police Facility HVAC System Improvements in an amount not-to-exceed $1,098,325 and cover the remaining project costs.
End
LocalBusinessEnterprise
Local Business Enterprise (LBE): Mesa Energy Systems, Inc. is not an LBE. The Kinney Police Facility HVAC Project includes federal ECBG funding and requires conformance with those requirements. Therefore, the City’s LBE policy is held in abeyance.
End