Title
Contract: Southside Park Pool Renovation (L19706500)
End
FileID
File ID: 2024-01095
End
Location
Location: 2115 6th Street, District 4, Represented by Councilmember Valenzuela
End
Recommendation
Recommendation: Pass a Motion: 1) awarding a construction contract to Dave Gross Enterprises Inc. dba Adams Pool Specialties in an amount not to exceed $594,921 for Southside Park Pool Renovation (L19706500); and 2) authorizing the City Manager or the City Manager’s designee to execute the contract specified above.
End
Contact
Contact: Richard Parks, Senior Architect, (916) 808-8427, rparks@cityofsacramento.org; David Avilla, Supervising Architect, (916) 808-7501, dravilla@cityofsacramento.org ; James Christensen, Facilities Manager, (916) 808-5863, jechristensen@cityofsacramento.org, Department of Public Works
End
Presenter
Presenter: None.
End
Attachments
Attachments:
1-Description/Analysis
2-Contract- Dave Gross Enterprises Inc. dba Adams Pool Specialties
End
Description/Analysis
IssueDetail
Issue Detail: The Department of Public Works Facilities and Real Property Management Division is seeking approval to award a construction contract to Adams Pool Specialties in an amount not to exceed $594,921 for Southside Park Pool Renovation.
The Southside Park Pool currently has a fiberglass finish that has deteriorated beyond its useful life, leading to the closure of the pool during the critical summer swim months. The degraded finish allows fibers to leach into the pool water, posing potential health risks to users.
To address these issues, the planned improvements involve removing the existing fiberglass finish, tiles, and other surfaces. The renovation will include installing new tiles, pool markings, depth markers, rope anchors, main drain covers, wall inlets and other fitting covers. All surfaces will be prepared for a new white plaster finish to ensure safety and functionality.
End
PolicyConsiderations
Policy Considerations: The recommendations in this report are in accordance with the provisions of City Code Chapter 3.60. which requires City Council approval of contracts of $250,000 or more.
End
EconomicImpacts
Economic Impacts: The recommended contract is expected to create 4.40 total jobs (2.80 direct jobs and 1.61 jobs through indirect and induced actives) and create $580,953 in total economic output ($372,406 of direct output and another $208,547 of output through indirect and induced activities).
The indicated economic impacts are estimates calculated using a calculation tool developed by the Center for Strategic Economic Research (CSER). CSER utilized the IMPLAN input-output model (2009 coefficients) to quantify the economic impacts of a hypothetical $1 million of spending in various construction categories within the City of Sacramento in an average one-year period. Actual impacts could differ significantly from the estimates and neither the City of Sacramento nor CSER shall be held responsible for consequences resulting from such differences.
End
EnvironmentalConsiderations
Environmental Considerations:
California Environmental Quality Act (CEQA): The action is exempt from review under the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15302. The action consists of the replacement or reconstruction of existing structures and facilities where the new structure will be located on the same site as the structure replaced and will have substantially the same purpose and capacity as the structure replaced. The action involves replacement or reconstruction of existing improvements and/or facilities involving negligible or no expansion of capacity.
End
Sustainability
Sustainability: None.
End
Commission/Committee Action
Commission/Committee Action: Not applicable.
End
RationaleforRecommendation
Rationale for Recommendation: The Southside Park Pool Renovation project will replace the deteriorating fiberglass pool surface with a new white plaster finish. These repairs will eliminate the potential health risks to patrons and staff and return the facility to an operational status.
On April 1, 2024, the Department of Public Works Facilities and Real Property Management Division issued Invitation for Bid (IFB) No. B24014541001 for Southside Park Pool Renovation. One bid was received. Dave Gross Enterprises Inc. dba Adams Pool Specialties met the LBE participation and is the lowest responsive and responsible bidder. The results of IFB No. B24014541001 are listed in the table below.
|
CONTRACTOR |
BID AMOUNT |
LBE % |
|
Dave Gross Enterprises Inc. dba Adams Pool Specialties. |
$594,921 |
Yes |
Construction is anticipated to begin in June of 2024
End
FinancialConsiderations
Financial Considerations: There is sufficient funding in the Southside Park Pool Repairs project (L19706500) (Fund 2401, Measure U and Fund 3204, Park Development) to award the contract to Dave Gross Enterprises Inc. dba Adams Pool Specialties, in the amount of $594,921 and cover the remaining project costs.
Due to the forecasted structural budget gap, the City Manager has directed City departments to minimize costs and for all new contracts to receive an additional level of scrutiny to ensure they are necessary for the operation of the City. This contract has been reviewed and approved by the City Manager’s Office to advance to Council for approval.
End
LocalBusinessEnterprise
Local Business Enterprise (LBE): Dave Gross Enterprises Inc. dba Adams Pool Specialties is an LBE.
End