Title: Vacation of a Portion of the Public Alley West of Stockton Boulevard Between 7th Avenue and 8th Avenue, Proceeding No. VAC26-0003 [Noticed 09/28/2026; Published 09/28/2026, 10/05/2026]
Attachments: 1. 2026-01713 STAFF REPORT
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Vacation of a Portion of the Public Alley West of Stockton Boulevard Between 7th Avenue and 8th Avenue, Proceeding No. VAC26-0003 [Noticed 09/28/2026; Published 09/28/2026, 10/05/2026]

End

 

FileID

File ID: 2026-01713

End

 

Location

Location: 3200 Block of Stockton Boulevard; District 5

End

 

Recommendation

Recommendation: Conduct a public hearing and upon conclusion: 1) pass a Motion to close the public hearing; and 2) adopt a Resolution vacating 16-foot-wide portion of the public alley.

End

 

Contact

Contact: Thomas Adams, Project Manager, (916) 808-7929, tadams@cityofsacramento.org; Chad Copeman, Supervising Engineer, (916) 808-1158, ccopeman@cityofsacramento.org; Ofelia Avalos, Engineering Manager, (916) 808-5055, oavalos@cityofsacramento.org; Department of Public Works

End

 

Presenter

Presenter: Thomas Adams, Project Manager, (916) 808-7929, tadams@cityofsacramento.org, Department of Public Works

End

 

Attachments

Attachments:

1-Description/Analysis

2-Resolution

3-Exhibit A - Legal Description of Public Alley to be Vacated

4-Exhibit B - Plat/Map of Public Alley to be Vacated

End

 

Description/Analysis

IssueDetail

Issue Detail: The Department of Public Works received a request to vacate a portion of the public alley located west of Stockton Boulevard between 7th Avenue and 8th Avenue as part of the proposed five-story multifamily development (DR24-093). The proposed multifamily development project will consist of 127 one, two and three bedroom multifamily units within the 0.78-acre site, covering 2 existing parcels currently located 3200 and 3258 Stockton Boulevard. As part of the project the existing commercial structures will be demolished and once approved, the abandoned alley will be incorporated as part of the proposed development project. Many of the existing utility facilities within the alley will require relocation and may necessitate the dedication of new easements, subject to the approval and satisfaction of the City's Department of Utilities and each affected utility service provider prior to the abandonment of the alley.

End

 

PolicyConsiderations

Policy Considerations: The City Council action recommended in this report is consistent with the Sacramento 2040 General Plan and in compliance with the California Streets and Highways Code sections 8300-8325.

End

 

EconomicImpacts

Economic Impacts: None.

End

 

EnvironmentalConsiderations

Environmental Considerations: The Community Development Department, Environmental Planning Services Division has reviewed this vacation of the existing 16’ wide alley and utility easement between 3200 and 3258 Stockton Blvd and determined that this is exempt from the provisions of the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15305, Minor Alteration in Land Use Limitation.  The project consists of the minor alteration in land use limitations with an average slope of less than 20%, which does not result in any changes in land use or density.

End

 

Sustainability

Sustainability: Not applicable.

End

 

Commission/Committee Action

Commission/Committee Action: None.

End

 

RationaleforRecommendation

Rationale for Recommendation: Adoption of the attached Resolution vacating the 16-foot-wide portion of the alley will help facilitate the proposed multifamily development by allowing the vacated alley area to be incorporated into the overall project site. Approval of the Resolution will support the development of additional housing that supports the City's housing development objectives.

End

 

FinancialConsiderations

Financial Considerations: The estimated cost to process this vacation request is approximately $5,000. The applicant is responsible for all fees required to process this application at no cost to the city.

End

 

LocalBusinessEnterprise

Local Business Enterprise (LBE): Not applicable.