Title
Preliminary Plans, Environmental Documentation Approval, and Budgetary Adjustments for the Fruitridge Road Improvements Phases 1 and 2 Project (T15036300)
End
FileID
File ID: 2026-00445
End
Location
Location: Fruitridge Road, between Stockton Boulevard and 65th Street Expressway, District 6
End
Recommendation
Recommendation: Adopt a Resolution: 1) finding the Fruitridge Road Improvements Project (T15036300) is exempt from the California Environmental Quality Act; [MJ1]2) approving the preliminary plans for the Fruitridge Road Improvements Phases 1 and 2 Project (T15036300); and 3) authorizing the City Manager or designee to increase the expenditure budget for Fruitridge Road Improvements - Phase 1 (T15036300) by transferring $120,000 (Major Street Construction, Fund 2007) and Phase 2 (T15036300) by transferring $640,000 (Major Street Construction, Fund 2007) from the expenditure budget of the State and Federal Grant Match Project (T15007200)[MJ2]; and 4) resetting the administrative authority for the Fruitridge Road Improvements Project (T15036300).
End
Contact
Contact: Stephanie Saiz, Assistant Civil Engineer, (916) 808-6808, ssaiz@cityofsacramento.org; Jesse Gothan, Supervising Engineer, (916) 808-6897, jgothan@cityofsacramento.org; Ofelia Avalos, Engineering Manager, (916) 808-5054, oavalos@cityofsacramento.org; Department of Public Works
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Resolution
3- Exhibit A - Preliminary Plans Phase 1
4- Exhibit B - Preliminary Plans Phase 2
End
Description/Analysis
IssueDetail
Issue Detail: The Fruitridge Road Improvements Project is made up of two phases for funding and delivery flexibility. Phase 1 is located on Fruitridge Road between 65th Street Expressway and Power Inn Road, and Phase 2 is located between Stockton Boulevard and 65th Street Expressway. The purpose of the Fruitridge Road Improvements Project is to calm traffic, improve mobility ...
Click here for full text