Title: [Contract] Sacramento Last Mile Project Package 4 (A07001800): Approval of Plans and Specifications [Published for 10-Day Review 11/19/2026]
Attachments: 1. 2026-02014 STAFF REPORT
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
[Contract] Sacramento Last Mile Project Package 4 (A07001800): Approval of Plans and Specifications [Published for 10-Day Review 11/19/2026]
End

FileID
File ID: 2026-02014
End

Location
Location: Districts 2, 4, 5, 6, 7, and 8
End

Recommendation
Recommendation: Pass a Motion: 1) approving the Plans and Specifications for the Sacramento Last Mile Project Package 4 (A07001800); 2) awarding the construction contract for the Sacramento Last Mile Project Package 4 (A07001800) to Pacific Excavation Inc. for an amount not-to-exceed $1,769,388; and 3) authorizing the City Manager or designee to execute the construction contract for the Sacramento Last Mile Project Package 4 (A07001800) to Pacific Excavation Inc. for an amount not-to-exceed $1,769,388.
End

Contact
Contact: Adam Randolph, Senior Engineer, (916) 808-7803, arandolph@cityofsacramento.org; Matthew Johns, Supervising Engineer, (916) 808-5760, mjohns@cityofsacramento.org; Ofelia Avalos, Engineering Services Manager, (916) 808-5054, oavalos@cityofsacramento.org; Department of Public Works
End

Presenter
Presenter: None
End

Attachments
Attachments:
1-Description/Analysis
2-Project Plans
3-Pacific Excavation Contract
End



Additional Description/Analysis
IssueDetail
Issue Detail: On September 29, 2023, staff applied for grant funding through the California Public Utilities Commission (CPUC) Last Mile Federal Funding Account (FFA) to implement the Sacramento Last Mile Connectivity Project to connect unserved communities to affordable broadband infrastructure. The unserved locations were selected based on criteria established by the CPUC's FFA program while overlaying the City network with the FFA Public Map, which identifies areas at the census block level lacking reliable broadband service of at least 25 Mbps downstream and 3 Mbps upstream. On September 13, 2024, the City received an award letter for $38,696,843 after the CPUC voted and approved the grant award in Resolution T...

Click here for full text