Title
[Contract] Arden Way Corrugated Metal Pipe (CMP) Storm Drains Replacement
End
FileID
File ID: 2026-01243
End
Location
Location: District 2
End
Recommendation
Recommendation: Pass a Motion: 1) approving the contract plans and specifications for the Arden Way Corrugated Metal Pipe (CMP) Storm Drains Replacement Project within the Drainage Collection System Rehabilitation and Replacement (R&R) Program (W14170100); 2) awarding the contract to Gravity Construction for an amount not-to-exceed $541,642; and 3) authorizing the City Manager or designee to execute the construction contract with Gravity Construction.
End
Contact
Contact: Brett Grant, Engineering Supervisor, (916) 808-1413, bgrant@cityofsacramento.org; Michelle Carrey, Engineering & Water Resources Division Manager, (916) 808-1438, mcarrey@cityofsacramento.org; Dalia Fadl, Director, (916) 808-3765, dfadl@cityofsacramento.org; Department of Utilities
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Contract
End
Description/Analysis
IssueDetail
Issue Detail: Staff recommends City Council award a construction contract to Gravity Construction, to replace approximately 400 lineal feet of CMP with PVC pipe, and approximately 22 lineal feet of reinforced concrete pipe (RCP) at four locations along Arden Way. This project also includes replacement of manholes and drainage inlets, and restoration of pavement, curb, gutter, sidewalk, and landscaping. All work will occur within the City right-of-way.
Segments of the existing drainage pipes in Arden Way have failed, or are at near failure and need to be replaced. Some pipes have fully collapsed causing localized flooding and several small sinkholes to develop in the roadway. The proposed project will reduce potential flooding by replacing these segments and restoring storm water conveyance and storage capacity during storms.
End
PolicyConsiderations
Policy Considerations: City Council...