Recommendation: Pass a Motion: 1) approving the construction plans and specifications for the Oakbrook Park Improvements (L19144100); 2) awarding the Oakbrook Park Improvements Project contract to Parker Landscape Development, Inc. in the amount of $338,728; and 3) authorizing the City Manager or the City Manager's designee to execute the contract.
End
Contact
Contact: Dennis Day, Senior Landscape Architect, (916) 380-8813, dday@cityofsacramento.org; Jason Wiesemann, Park Planning and Development Services Manager, (916) 808-7634, jwiesemann@cityofsacramento.org; Department of Youth, Parks, & Community Enrichment
End
Presenter
Presenter: None.
End
Attachments
Attachments:
1-Description/Analysis
2-Contract[RM1][DD2]
End
Description/Analysis
IssueDetail
Issue Detail: The Department of Youth, Parks & Community Enrichment (YPCE) is seeking approval to award a contract to Parker Landscape Development, Inc. for the Oakbrook Park Improvement Project (L19144100). The contract amount is $338,728.
The contract work consists of clearing and grubbing, grading, concrete flatwork, curbs, mow strips, decomposed granite paving, chain link fencing and gates, raised and accessible planter beds, a concrete seat wall, a hose bib irrigation system, a 10'x 12' storage shed, two picnic tables, imported soil mix, a removable bollard, six fruit trees and a message board.
The formal bid process for this project has been completed and Parker Landscape Development, Inc. has been selected as the lowest responsible and responsive bidder. Construction of the Oakbrook Park Improvements Project is expected to be completed in Fall 2024. Oakbrook Park is a 4.8-acre neighborhood park located at 3341 Soda Way, Planning Area 9, Council District 3.