Title: [Contract] Pocket Road Sewer Replacement at East Shore Project
Attachments: 1. 2026-00865 STAFF REPORT
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
[Contract] Pocket Road Sewer Replacement at East Shore Project
End

FileID
File ID: 2026-00865
End

Location
Location: District 7
End

Recommendation
Recommendation: Pass a Motion: 1) approving the contract plans and specifications for the Pocket Road Sewer Replacement at East Shore Project (X14120300); 2) awarding the contract to Subterra Construction, Inc. for an amount not to exceed $457,600, and 3) authorizing the City Manager or designee to execute the construction contract with Subterra Construction, Inc.
End

Contact
Contact: Angelo Vasquez, Project Manager (916) 808-1701, arvasquez@cityofsacramento.org; Sherill Huun, Engineering & Water Resources Division Manager, (916) 808-1455, shuun@cityofsacramento.org; Dalia Fadl, Director, (916) 808-3765, dfadl@cityofsacramento.org; Department of Utilities
End

Presenter
Presenter: None
End

Attachments
Attachments:
1-Description/Analysis
2-Construction Contract - Subterra Construction, Inc.
End

Description/Analysis
IssueDetail
Issue Detail: Staff recommends City Council award a construction contract to Subterra Construction, Inc., to perform all the work necessary to remove and replace roughly 50 linear feet of separated sewer pipe, remove and replace the damaged manhole, and repave along the intersection of Pocket Road and East Shore Drive.

This location was identified as a high priority due to the roadway depression that has been reported by residents in the area that has been slowly developing over the years. City Operations and Maintenance staff confirmed that the sewer manhole in the area had settled and was taking on groundwater.

The Department of Utilities recently dealt with an emergency project in 2023 that was located further east on Pocket Road. That project started out similarly and highlighted the vulnerability of this area's subsurface conditions and has since prompted heightened monitoring and proactive planning by City Staff.