Recommendation
Recommendation: Pass a Motion: 1) authorizing the City Manager or designee to execute Change Order No. 2 to City Agreement No. PRC004314 with Steve P. Rados, Inc., for an amount not to exceed $639,166, bringing the agreement’s total not-to-exceed amount to $3,589,971; and 2) resetting the City Manager or designee’s authority to issue contract amendments for the Agreement.
End
Contact
Contact: Tim Moresco, Project Manager, (916) 808-1432, tmoresco@cityofsacramento.org; Michelle Carrey, Engineering & Water Resources Division Manager, (916) 808-1438, mcarrey@cityofsacramento.org; Dalia Fadl, Director, (916) 808-3765, dfadl@cityofsacramento.org; Department of Utilities
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Change Order
End
Description/Analysis
IssueDetail
Issue Detail: Staff recommend City Council approve Change Order No. 2 with Steve P. Rados, Inc., on Agreement No. PRC004314 in the amount of $639,166 to compensate the Contractor for installing an additional 136 linear feet of Fiberglass Reinforced Plastic (FRP) pipe on the North 5th Street Parallel Trunk Main Project. The original contract scope was completed under budget, and eligible grant funding remained available. To fully utilize the remaining funds, the City advanced work eligible to receive grant funding that had previously been planned for a future phase. With this change order, the contract’s total not-to-exceed amount will increase from $2,950,804 to $3,589,970.
The project is funded by reimbursement through the Sacramento Area Council of Governments (SACOG) Green Means Go grant, which supports stormwater infrastructure improvements and future development within the River District. All work must comply with the requirements of the funding agreeme...
Click here for full text