Title
[Contract] Award Construction Contract for Bertha Henschel Park Restroom and Basketball Court Improvements
End
FileID
File ID: 2026-01225
End
Location
Location: District 4
End
Recommendation
Recommendation: Pass a Motion: 1) approving the construction plans and specifications for the Bertha Henschel Park Restroom and Basketball Court Improvements Project; 2) awarding the construction contract for the Bertha Henschel Park Restroom and Basketball Court Improvements Project to Parker Landscape Development, Inc. in an amount not-to-exceed $277,686; and 3) authorizing the City Manager or designee to execute the construction contract.
End
Contact
Contact: Dennis Day, Senior Landscape Architect, (916) 808-7633, dday@cityofsacramento.org; Jason Wiesemann, Park Planning, Design, and Development Manager, (916) 808-7634, jwiesemann@cityofsacramento.org; Department of Youth, Parks, and Community Enrichment
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Contract
End
Description/Analysis
IssueDetail
Issue Detail: The Department of Youth, Parks, and Community Enrichment (YPCE) requests approval to award a contract to Parker Landscape Development, Inc. for the Bertha Henschel Park Restroom and Basketball Court Improvements Project for $277,686. The project scope includes: demolishing the existing restroom building, concrete flatwork, and wood shade structure; preparing the pad and utilities for a new restroom; and coordinating installation with the Public Restroom Company. Additional improvements include constructing new concrete flatwork and a 6-inch curb, replacing the drinking fountain and basketball equipment, applying an asphalt seal coat, restriping both courts, relocating turf rotors, providing turf seeding and landscape maintenance, and installing new picnic tables and a concrete park sign.
Following completion of the formal bidding process, Parker Landscape Development, Inc. was identified...