[Contract] 2026 Relief Wells Inspection, Testing, and Rehabilitation
End
FileID
File ID: 2026-00751
End
Location
Location: Citywide
End
Recommendation
Recommendation: Pass a Motion authorizing the City Manager or designee to execute a Professional Services Agreement with Kleinfelder, Inc. to rehabilitate, test, and inspect 66 relief wells for the Sacramento Area Flood Control Agency (SAFCA) Levee Maintenance Project (I14120300), for an amount not to exceed $598,450.
End
Contact
Contact: Gary Gulseth, Project Manager, (916) 808-1415, ggulseth@cityofsacramento.org; Sherill Huun, Engineering & Water Resources Division Manager, (916) 808-1455, shuun@cityofsacramento.org; Dalia Fadl, Director, (916) 808-3765, dfadl@cityofsacramento.org; Department of Utilities
End
Presenter
Presenter: None
End
Attachments
Attachments:
1-Description/Analysis
2-Agreement
End
Description/Analysis
IssueDetail
Issue Detail: Staff recommends the City Council approve an agreement with Kleinfelder Inc., for rehabilitation, testing, and inspection of 66 relief wells. Between 2006 and 2017, the United States Army Corps of Engineers (Corps) installed 66 relief wells along levees in the City of Sacramento (City) to relieve hydrostatic pressure in the substrata adjacent to levees. These wells are located along the east side of the Sacramento River and the north side of North Beach Lake (Morrison Creek). In July 2007, the City signed an agreement (City Agreement No. 2007-1307) with the Sacramento Area Flood Control Agency (SAFCA) to perform prescribed maintenance and testing per guidelines established by the Corps every five (5) years. The obligations from the 2007 agreement with SAFCA remain in force.
End
PolicyConsiderations
Policy Considerations: City Council approval is required for professional service agreements of $250,000 or more per City Code 3.56.090.
End
EconomicImpacts
Economic Impacts: None.
End
EnvironmentalConsiderations
Envi...