Legislation Details

File #: 2026-00857    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 4/2/2026 In control: City Council - 2PM
On agenda: 5/5/2026 Final action:
Title: [Memorandum of Understanding] Fund Transfer from North Sacramento-Hagginwood Library Relocation (NSHLR) Project (C15000850) to Sacramento Public Library (SPL) and Change Order John F. Otto Inc., dba Otto Construction
Attachments: 1. 2026-00857 STAFF REPORT
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
[Memorandum of Understanding] Fund Transfer from North Sacramento-Hagginwood Library Relocation (NSHLR) Project (C15000850) to Sacramento Public Library (SPL) and Change Order John F. Otto Inc., dba Otto Construction
End

FileID
File ID: 2026-00857
End

Location
Location: 1124 Del Paso Boulevard, District 2
End

Recommendation
Recommendation: 1) pass a Motion: a) authorizing the City Manager or designee to execute Change Order No. 3 to Contract No. 2025-4573 with John F. Otto Inc. dba Otto Construction, for an amount not-to-exceed $207,754 for a new total amount not-to-exceed of $7,823,339; b) ratifying Change Orders 1 and 2 for this project issued under City Manager authority; and c) resetting the City Manager's or designee's authority to issue change orders for Contract No. 2025-4573; and 2) adopt a Resolution: a) authorizing the City Manager or designee to execute a Memorandum of Understanding (MOU) between the City of Sacramento and the Sacramento Public Library Authority (SPL) in an amount not-to-exceed $430,000 for the North Sacramento-Hagginwood Library Relocation Project (NSHLR); and b) transferring $430,000 (General Fund, Fund 1001) from North Sacramento-Hagginwood Library Relocation Project C15000850 to the SPL CIP.
End

Contact
Contact: Ezra Roati, Senior Architect, (916) 808-5877, eroati@cityofsacramento.org; David Avila, Supervising Architect, (916) 808-7501, dravila@cityofsacramento.org; James Christensen, Facilities Manager, (916) 808-5863, jechristensen@cityofsacramento.org; Department of Public Works
End

Presenter
Presenter: None
End

Attachments
Attachments:
1-Description/Analysis
2-Resolution
3-Change Order No. 3 - John F. Otto Inc., dba Otto Construction
End

Description/Analysis
IssueDetail
Issue Detail: The City of Sacramento, in collaboration with SPL, is undertaking the renovation of an existing building and relocation of the North Sacramento-Hagginwood Library to address the community's growing need for ...

Click here for full text