File #: 2019-01030    Version: 1
Type: Consent Item Status: Agenda Ready
File created: 6/27/2019 In control: City Council - 2PM
On agenda: 7/30/2019 Final action: 12/31/2023
Title: Budgetary Adjustments: West El Camino Avenue Widening and Bridge Replacement Project (T15008200)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title:

Title

Budgetary Adjustments: West El Camino Avenue Widening and Bridge Replacement Project (T15008200)

End

 

FileID

File ID: 2019-01030

 

Location

Location: West El Camino Avenue between Interstate 80 and Gateway Oaks Drive; Orchard Lane between Barandas Way and 300 feet north of West El Camino Avenue; District 4

 

Recommendation:

Recommendation

Adopt a Resolution authorizing the City Manager or the City Manager’s designee to: 1) increase the Fiscal Year 2019/20 Department of Public Works revenue budget by $144,636 (Fair Share Contribution Fund, Fund 2032) to reflect the March 23, 2019 fair share contribution; 2) increase the expense budget in the West El Camino Avenue Widening and Bridge Replacement Project (T15008200) by $144,636 (Fair Share Contribution Fund, Fund 2032); 3) reduce the expense budget in the West El Camino Avenue Widening and Bridge Replacement Project (T15008200) by $144,636 (Major Street Construction Fund, Fund 2007); and 4) increase the available fund balance of the Major Street Construction Fund (Fund 2007) by $144,636.

 

Contact: Dustin Purinton, Senior Accountant Auditor (916) 808-5587; Nader Kamal, Interim Engineering Services Manager (916) 808-7035, Department of Public Works

 

Body

Presenter: None

 

Attachments:

1-Description/Analysis

2-Resolution

 

 

 

Description/Analysis

 

Issue Detail: On August 12, 2003, the City Council adopted Resolution No. 2003-0562 appropriating funds and awarding a contract to construct the West El Camino Avenue Widening and Bridge Replacement Project (T15008200). The City advanced local transportation funds to complete the West El Camino Avenue Widening and Bridge Replacement Project (T15008200) with the understanding that upon development of the property the City would be reimbursed.

 

On August 30, 2018, the Planning and Design Commission approved the Notice of Decision for the Tentative Map of the Core Natomas Project (P18-011). As a condition of approval, the developer was required to construct West El Camino Avenue in accordance with the West El Camino Widening and Bridge Replacement Project (T15008200) and pay any associated fair share fees.

 

On March 23, 2019, the City received a fair share contribution of $144,636 from the Core Natomas Project. Budgeting the fair share funding of $144,636 (Fund 2032) in the West El Camino Avenue Widening and Bridge Replacement Project (T15008200) is consistent with the conditions of approval.

 

Policy Considerations: Not applicable.

 

Economic Impacts: None.

 

Environmental Considerations:

 

California Environmental Quality Act (CEQA): Budgetary adjustments are not subject to the provisions of the CEQA. Under CEQA general rule 15061(B)(3), CEQA applies only to projects which have the potential for causing a significant effect on the environment. These actions will have no effect on the environment, thus are not subject to CEQA.

 

Appropriate CEQA and National Environmental Policy Act (NEPA) review was completed as part of project development.

 

Sustainability: Not applicable.

 

Commission/Committee Action: None.

 

Rationale for Recommendation: Approval of the budgetary adjustments to accept the fair share contribution and return the prior year Major Street Construction (Fund 2007) funds to available fund balance will complete the repayment of the construction advance for the Core Natomas Project.

 

Financial Considerations: The City advanced local transportation funds to complete the West El Camino Avenue Widening and Bridge Replacement Project (T15008200) with the understanding that upon development of the property the City would be reimbursed.

 

On March 23, 2019, the developer of the Core Natomas Project paid their fair share contribution in the amount of $144,636 per the conditions of approval approved by the Planning and Design Commission Notice of Decision P18-011.

 

Approval of the budgetary adjustments to increase the Fiscal Year 2019/20 Department of Public Works revenue budget by $144,636 (Fair Share Contribution Fund, Fund 2032), increase the expense budget in the West El Camino Avenue Widening and Bridge Replacement Project (T15008200) by $144,636 (Fair Share Contribution Fund, Fund 2032), reduce the expense budget in the West El Camino Avenue Widening and Bridge Replacement Project (T15008200) by $144,636 (Major Street Construction, Fund 2007), and increase the available fund balance of the Major Street Construction Fund (Fund 2007) will complete the repayment of the construction advance for the Core Natomas Project.  

 

There are no General Funds planned or allocated for this project.

 

Local Business Enterprise (LBE): Not applicable.