Supplemental Agreement: Rio Linda Boulevard Bridge Replacement and Main Avenue Realignment Project (T15095200)
End
FileID
File ID: 2019-00574
Location
Location: Rio Linda Boulevard and Main Avenue, District 2
Recommendation:
Recommendation
Pass a Motion: 1) authorizing the City Manager or the City Manager’s designee to execute Supplemental Agreement No. 15 to City Agreement No. 2011-1290 with Mark Thomas & Company, Inc. in an amount not to exceed $93,856, for a new total not to exceed amount of $829,500; and 2) resetting the City Manager’s authority to issue supplemental agreements for City Agreement No. 2011-1290.
Contact: Philip Vulliet, Senior Civil Engineer, (916) 808-5092; Nader Kamal, Interim Engineering Services Manager, (916) 808-7035, Department of Public Works
Body
Presenter: None
Attachments:
1-Description/Analysis
2-Consultant Supplemental Agreement - Mark Thomas and Company (2011-1290)
Description/Analysis
Issue Detail: The Rio Linda Boulevard Bridge Replacement and Main Avenue Realignment Project will replace the existing structurally deficient bridge over Magpie Creek and realign the creek to the south. The intersection will be widened to accommodate turn pockets, and Main Avenue will be realigned to intersect perpendicular to Rio Linda Boulevard. The improvements will include an improved intersection with left and right turn pockets and Class II bike lanes on both Rio Linda Boulevard and Main Avenue.
The project will enhance safety on Rio Linda Boulevard and Main Avenue by improving sight distance, decreasing vehicle queuing conflicts with turn pockets, and increasing the roadway shoulders to meet City standards. This project will improve traffic operations, realign Main Avenue into the existing City right-of-way, and improve pedestrian connectivity with the Sacramento Northern Bike Trail.
City Council passed a resolution to award the construction contract and a consultant contract for construction management services on March 26, 2019. A corresponding supplemental agreement with the consultant design team is required for ongoing design support activities throughout the two-year construction phase.
Policy Considerations: The action requested supports the City’s General Plan goals of improving the transportation system, expanding public safety, achieving sustainability through reduced dependence on the private automobile, and enhancing livability and economic vitality.
Economic Impacts: None
Environmental Considerations:
California Environmental Quality Act and National Environmental Policy Act (CEQA/NEPA): The City adopted a Mitigated Negative Declaration (MND) in compliance with CEQA on October 29, 2013.
The project is funded by federal Highway Bridge Program funds. As a result, the proposed project is also subject to NEPA requirements. On November 21, 2013, Caltrans approved a Categorical Exclusion for the project pursuant to the requirements of NEPA.
Sustainability: This project is consistent with General Plan goals of improving the transportation system, expanding public safety, creating a well-connected transportation network, conserving energy resources, reducing greenhouse gas emissions and air pollution, and do so while continuing to accommodate auto mobility.
Commission/Committee Action: None
Rationale for Recommendation: Approval of Supplemental Agreement No. 15 with Mark Thomas & Company, Inc. will enable the City to complete the construction of the Rio Linda Boulevard Bridge Replacement and Main Avenue Realignment Project including all of the required design oversight and input during construction.
Financial Considerations: The total estimated cost of the Rio Linda Boulevard Bridge Replacement and Main Avenue Realignment Project (T15095200) is approximately $10.7 million. There is sufficient funding available in the project to execute Supplemental Agreement No. 15 with Mark Thomas & Company, Inc. in the amount of $93,856 and cover the remaining construction and construction management costs.
There are no General Funds planned or allocated for this project.
Local Business Enterprise (LBE): The contract with Mark Thomas and Company Inc. is a federally funded contract and as a result Disadvantaged Business Enterprise (DBE) project participation requirements apply. LBE rules are held in abeyance. The contract award will comply with all federal DBE participation requirements. Mark Thomas has pledged 12.7% DBE project participation, exceeding the 1.94% DBE goal set for this contract.
Background: The following is a summary of previous supplements that have been executed on the subject contract:
Supplemental Agreement No. 1 had no budget impact and was executed on May 8, 2012 to approve adding staff to the consultant team.
Supplemental Agreement No. 2 had no budget impact and was executed on July 13, 2012 to modify staffing and rates for the consultant team.
Supplemental Agreement No. 3 had no budget impact and was executed on August 22, 2012 to add contract rates for environmental consultants to the consultant team.
Supplemental Agreement No. 4 had no budget impact and was executed on September 27, 2012 to modify staffing and update rates for the consultant team.
Supplemental Agreement No. 5 had no budget impact and was executed on March 7, 2013 to add staff to the consultant team.
Supplemental Agreement No. 6 had no budget impact and was executed on June 13, 2013 to extend the contract sunset date and add staff to the consultant team.
Supplemental Agreement No. 7 had no budget impact and was executed on October 23, 2013 to update contract documents to current City standards.
Supplemental Agreement No. 8 had no budget impact and was executed on June 3, 2014 to reallocate budget and add staff to the consultant team.
Supplemental Agreement No. 9 had no budget impact and was executed on July 15, 2015 to extend the contract sunset date.
Supplemental Agreement No. 10 in the amount of $79,045.84 was executed on November 18, 2015 to perform additional design and hydraulic analysis.
Supplemental Agreement No. 11 had no budget impact and was executed on April 12, 2017 to update contract rates for prevailing wage employees.
Supplemental Agreement No. 12 had no budget impact and was executed on June 26, 2017 to extend the contract sunset date.
Supplemental Agreement No. 13 in the amount of $58,292.81 was executed on September 27, 2017 to perform additional design support for the eminent domain process for right of way acquisition.
Supplemental Agreement No. 14 had no budget impact and was executed on December 18, 2018 to extend the contract sunset date.