Title: Stockton Boulevard Safety and Transit Enhancement Project (T15245100)
Attachments: 1. 2026-00671 Stockton Boulevard Safety and Transit Enhancement Project (T15245100)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

Title

Stockton Boulevard Safety and Transit Enhancement Project (T15245100)

End

 

FileID

File ID: 2026-00671

End

 

Location

Location: Stockton Boulevard, between Alhambra Blvd and Florin Road, and Bus Routes 38 and 51, District 4, 5, and 6

End

 

Recommendation

Recommendation: Review and comment.

End

 

Contact

Contact: Jesse Gothan, Supervising Engineer, (916) 808-6897, jgothan@cityofsacramento.org, Department of Public Works

End

 

Presenter

Presenter: Jesse Gothan, Supervising Engineer, (916) 808-6897, jgothan@cityofsacramento.org, Department of Public Works

End

 

Attachments

Attachments:

1-Description/Analysis

2-Presentation

End

 

Additional Description/Analysis

IssueDetail

Issue Detail: The City of Sacramento has taken the lead in a multi-jurisdictional partnership with Sacramento County and the Sacramento Regional Transit District (SacRT) to evaluate multimodal and safety improvements along Stockton Boulevard, including bus lanes and other transit enhancements, bicycle facilities, and pedestrian upgrades. This project has two primary goals, to create a safer, multimodal corridor and to increase transit ridership. Stockton Blvd includes two of the top five corridors for traffic fatalities and serious injuries.  The Stockton Boulevard Safety and Transit Enhancement Project (STEP) will also include an alternatives analysis for Bus Rapid Transit (BRT) treatments along SacRT’s Route 51 or 38 alignments between South Sacramento and the Sacramento Valley Station. The installation of BRT treatments along Stockton Boulevard will provide a direct, convenient, and safe travel route for community residents, while pedestrian and bicycle improvements will provide convenient access for surrounding neighborhoods to the community center, essential resources, and economic centers - both adjacent to this corridor and accessible by public transportation.

 

Through two rounds of Sacramento Area Council of Government (SACOG) grant funding programs, the City and its partner agencies have been awarded both Federal and State funds to complete preliminary engineering and environmental clearance.

 

This phase of the project will develop alternatives sufficient to identify the preferred alternative and provide environmental documentation. Staff is requesting the Active Transportation Commission’s feedback and comments on the priorities of the proposed alternatives.

End

 

PolicyConsiderations

Policy Considerations: The action requested supports the City’s General Plan goals of improving the transportation system.

 

General Plan M 1.1.2, providing multimodal choices

 

General Plan M 1.2.1, providing multimodal access to activity centers such as commercial corridors, employment centers, and transit stops

 

General Plan M 1.2.4, improving transit access

 

General Plan M 1.3.3, increasing transit service

 

General Plan M 3.1.2, filling gaps in complete streets

 

General Plan M 4.2.6, providing much needed improvements to the bicycle and pedestrian facilities for continuous mobility and connectivity, while expanding transit access and achieving sustainability through reduced dependence on the private automobile.

End

 

EconomicImpacts

Economic Impacts:  Not applicable.

End

 

EnvironmentalConsiderations

Environmental Considerations: Once selected, the project will complete state and federal environmental reviews of the preferred alternatives as part of future actions.  Under CEQA general rule 15061(B)(3), CEQA applies only to projects which have the potential for causing a significant effect on the environment. These actions are review and comment and will have no effect on the environment, thus are not subject to CEQA.

 

Federal funds have been appropriated for the project and is, therefore, subject to National Environmental Policy Act (NEPA) review. The appropriate CEQA and NEPA review will take place as part of project development and approval.

End

 

Sustainability

Sustainability: The proposed project supports City Council’s sustainability priorities. The transportation sector accounts for 57% of community-wide greenhouse gas emissions, the largest single sector in the community. The City’s Climate Action Plan includes several implementation measures to reduce vehicle trips. The project would increase active transportation, reduce vehicular trips, and help ensure more efficient vehicular flow. These actions will reduce greenhouse gas emissions and help improve local air quality.

End

 

Commission/Committee Action

Commission/Committee Action: None.

End

 

RationaleforRecommendation

Rationale for Recommendation: The action requested is to update the Commission on the project and share public engagement opportunities with their communities.

End

 

FinancialConsiderations

Financial Considerations: The funding for the Stockton Boulevard STEP alternatives analysis is fully funded with state and federal grants.

End

 

LocalBusinessEnterprise

Local Business Enterprise (LBE): Not applicable.