File #: 2018-01523    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 10/25/2018 In control: City Council - 5PM
On agenda: 11/8/2018 Final action: 12/31/2023
Title: Change Order: Memorial Auditorium Improvement Project (M17100100)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title:
Title
Change Order: Memorial Auditorium Improvement Project (M17100100)
End

FileID
File ID: 2018-01523

Location
Location: 1515 J Street, District 4

Recommendation:
Recommendation
Pass a Motion: 1) authorizing the City Manager or the City Manager's designee to execute Change Order No. 4 to City Agreement No. 2017-0677 in an amount not to exceed $35,852 with Kitchell CEM, Inc., for a new total not-to-exceed amount of $11,010,542; 2) increasing Change Order Authority for the Construction Phase of the Memorial Auditorium Improvement Project; and 3) resetting the City Manager's authority to issue change orders for City Agreement No. 2017-0677.

Contact: Sabrina Tefft, Project Manager, (916) 808-3789, Ofelia Avalos, Senior Engineer, (916) 808-5054; Fran Halbakken, Assistant City Manager/Project Executive, (916) 808-7194; Office of the City Manager

Body
Presenter: None

Attachments:
1-Description/Analysis
2-Change Order No. 4 to Agreement No. 2017-0677



Description/Analysis

Issue Detail: Improvements to the Memorial Auditorium are needed to relocate Community Center Theater events to the Memorial Auditorium while the Theater is under construction.

On January 24, 2017, City Council approved an agreement with Kitchell CEM, Inc. to provide design-assist and pre-construction services for the improvements to Memorial Auditorium in the amount of $177,804 with an option for a Guaranteed Maximum Price (GMP). On May 29, 2017 City Council approved the GMP and authorized Kitchell CEM, Inc. to proceed with construction through an amendment to Kitchell's contract in the amount of $10,739,169 for the construction of the Memorial Auditorium upgrades and changed the contract from design-assist to a construction contract to initiate construction work.

Increasing the Change Order Authority for the project is needed to reflect the change from the design portion of the Design-Assist contract of $177,804 to the revised project basis for Construction of $10,73...