Title: Change Order and Supplemental Agreements for Shasta Park Reservoir and Pump Station Project
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title:
Title
Change Order and Supplemental Agreements for Shasta Park Reservoir and Pump Station Project
End

FileID
File ID: 2019-00316

Location
Location: District 8

Recommendation:
Recommendation
Pass a Motion: 1) authorizing the City Manager or the City Manager's designee to execute Change Order No. 13 to City Agreement No. 2016-1073 with Sierra National Construction, Inc., for an amount not-to-exceed $536,520, bringing the agreement's total not-to-exceed amount to $14,740,533; 2) resetting the City Manager's authority to issue Change Orders for Agreement No. 2016-1073; 3) authorizing the City Manager or the City Manager's designee to execute Supplemental Agreement No. 8 to City Agreement 2012-0654 with Wood Rodgers for an amount not-to-exceed $254,584, bringing the agreement's total not-to-exceed amount to $1,410,026; 4) resetting the City Manager's authority to issue Supplemental Agreements for Agreement No. 2012-0654; 5) authorizing the City Manager or the City Manager's designee to execute Supplemental Agreement No. 6 to City Agreement No. 2016-1011 with West Yost Associates, for an amount not-to-exceed $129,109, bringing the agreement's total not-to-exceed amount to $1,456,292; and 6) resetting the City Manager's authority to issue Supplemental Agreements for Agreement No. 2016-1011.

Contact: Peter Wright, Project Manager (916) 808-1433; Michelle Carrey, Supervising Engineer (916) 808-1438; Dan Sherry, Engineering & Water Resources Division Manager, (916) 808-1419; Department of Utilities

Body
Presenter: None

Attachments:
1-Description/Analysis
2-Change Order No. 13, Sierra National Construction, Inc.
3-Supplemental Agreement No. 8, Wood Rodgers
4-Supplemental Agreement No. 6, West Yost



Description/Analysis

Issue Detail: Staff recommends Council approve Change Order No. 13 with Sierra National Construction, Inc., for modifications due to design changes and to improve operations and constructability.

Staff recommends Council approve...

Click here for full text