Title:
Title
Change Order and Supplemental Agreements for Shasta Park Reservoir and Pump Station Project
End
FileID
File ID: 2019-00316
Location
Location: District 8
Recommendation:
Recommendation
Pass a Motion: 1) authorizing the City Manager or the City Manager's designee to execute Change Order No. 13 to City Agreement No. 2016-1073 with Sierra National Construction, Inc., for an amount not-to-exceed $536,520, bringing the agreement's total not-to-exceed amount to $14,740,533; 2) resetting the City Manager's authority to issue Change Orders for Agreement No. 2016-1073; 3) authorizing the City Manager or the City Manager's designee to execute Supplemental Agreement No. 8 to City Agreement 2012-0654 with Wood Rodgers for an amount not-to-exceed $254,584, bringing the agreement's total not-to-exceed amount to $1,410,026; 4) resetting the City Manager's authority to issue Supplemental Agreements for Agreement No. 2012-0654; 5) authorizing the City Manager or the City Manager's designee to execute Supplemental Agreement No. 6 to City Agreement No. 2016-1011 with West Yost Associates, for an amount not-to-exceed $129,109, bringing the agreement's total not-to-exceed amount to $1,456,292; and 6) resetting the City Manager's authority to issue Supplemental Agreements for Agreement No. 2016-1011.
Contact: Peter Wright, Project Manager (916) 808-1433; Michelle Carrey, Supervising Engineer (916) 808-1438; Dan Sherry, Engineering & Water Resources Division Manager, (916) 808-1419; Department of Utilities
Body
Presenter: None
Attachments:
1-Description/Analysis
2-Change Order No. 13, Sierra National Construction, Inc.
3-Supplemental Agreement No. 8, Wood Rodgers
4-Supplemental Agreement No. 6, West Yost
Description/Analysis
Issue Detail: Staff recommends Council approve Change Order No. 13 with Sierra National Construction, Inc., for modifications due to design changes and to improve operations and constructability.
Staff recommends Council approve...