City of Sacramento header
File #: 2019-01227    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 8/9/2019 In control: City Council - 2PM
On agenda: 9/10/2019 Final action:
Title: Supplemental Agreement and Transfer of Funds: Sacramento Valley Station Phase 3B Master Plan & Railyards Specific Plan Amendment (T15029000) [Published for 10-Day Review 08/29/2019]
Indexes: Budget Change
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title:
Title
Supplemental Agreement and Transfer of Funds: Sacramento Valley Station Phase 3B Master Plan & Railyards Specific Plan Amendment (T15029000) [Published for 10-Day Review 08/29/2019]
End

FileID
File ID: 2019-01227

Location
Location: Districts 3 and 4, 401 I Street

Recommendation:
Recommendation
Adopt a Resolution: 1) authorizing the City Manager or the City Manager's designee to transfer $177,238 (Development Services Fund, Fund 2016) from the expenditure budget of the General Plan Update Program (I22000000) to the expenditure budget of the Intermodal Transportation Facility Project (T15029000); 2) authorizing the City Manager or the City Manager's designee to execute Supplemental Agreement No. 10 to City Agreement No. 2016-1397 with Perkins + Will Architects in an amount not to exceed $1,134,825, for a new total not to exceed amount of $3,327,406; and 3) resetting the City Manager's authority to issue supplemental agreements to City Agreement No. 2016-1397.

Contact: Gregory Taylor, AIA, LEED AP, Project Manager, (916) 808-5268; Ryan Moore, Interim Director of Department of Public Works, (916) 808-6629, Department of Public Works

Body
Presenter: None.

Attachments:
1-Description/Analysis
2-Resolution
3-Supplemental Agreement No. 10


Description/Analysis

Issue Detail: The Sacramento Valley Station Phase 3B Master Plan commenced in November 2016 with a contract to produce two conceptual plan options for the site for expansion of the station complex and allocation of developable area to create a transit hub district. This work is funded with Measure A funds related to the transportation use of the property, and General Funds for the non-transportation scope of work related to supportive development. Additional funding is needed to complete the analysis and adopt it as an amendment to the Railyards Specific Plan. Those funds will come from the General Plan Update Program (I22000000).

Policy Considerations: The recommendation in this rep...

Click here for full text