Title: Supplemental Agreement No. 2 with BCA Architects and Tree Removal for the North Natomas Community Center and Aquatic Complex Project (L19140410)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title:
Title
Supplemental Agreement No. 2 with BCA Architects and Tree Removal for the North Natomas Community Center and Aquatic Complex Project (L19140410)
End

FileID
File ID: 2019-01259

Location
Location: District 1, North Natomas Regional Park between Town Center Drive and Via Ingoglia

Recommendation:
Recommendation
Pass a Motion: 1) authorizing the City Manager or the City Manager's designee to execute Supplemental Agreement No. 2 to City Agreement No. 2017-1254 with BCA Architects for an amount not to exceed $619,500, for a new total not-to-exceed amount of $2,723,212; and 2) authorizing the removal of 26 trees at the NNCCAC site and replacement with 270 new trees.

Contact: Kirk Thompson, Senior Architect, (916) 808-8431; James Christensen, Facilities Manager, (916) 808-5863, Department of Public Works; Jason Wiesemann, Senior Landscape Architect, (916) 808-7634, Department of Youth, Parks, and Community Enrichment

Body
Presenter: None

Attachments:
1-Description/Analysis
2-Supplemental Agreement No. 2



Description/Analysis

Issue Detail: Approval of Supplemental Agreement No. 2 with BCA Architects in the amount of $619,500 is necessary so BCA Architects can provide construction support services during the approximately 16-month construction period of the North Natomas Community Center and Aquatics Complex (NNCCAC) project (the "Project").

To construct the Project, removal of 26 trees with a total diameter at standard height (DSH) of 111.75" from the Project site is necessary. The trees are as follows: One Tulip tree with 1.5" DSH, one Chinese Tallow with 5.5" DSH, eight Sycamores with a total DSH of 43", six Zelkova trees with a total DSH of 21", and ten Valley Oaks with a total DSH of 40.75". Construction plans were adjusted to save existing trees where possible. The trees were posted for removal at the Project site on August 26, 2019 pursuant to City Code section 12.56.040.

Policy Considerations: The recommendations in this report a...