City of Sacramento header
File #: 2019-01618    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 10/28/2019 In control: City Council - 2PM
On agenda: 12/10/2019 Final action:
Title: Contract and Fund Transfers for Meadows Community Park Phase 1 Project (Published for 10-Day Review 11/27/2019)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title:
Title
Contract and Fund Transfers for Meadows Community Park Phase 1 Project (Published for 10-Day Review 11/27/2019)
End

FileID
File ID: 2019-01618

Location
Location: District 1

Recommendation:
Recommendation
Adopt a Resolution: 1) approving the construction plans and specifications for the Meadows Community Park Phase 1 Project (L19138100); 2) awarding the contract to Marina Landscape, Inc. in the amount of $2,360,400; 3) authorizing the City Manager or the City Manager's designee to execute the contract; and 4) authorizing the City Manager or the City Manager's designee to increase the expenditure budget in L19138100 by transferring $650,000 from Park Development Impact Fees (Fund 3204) available fund balance.

Contact: Tin-Wah Wong, Landscape Architect, (916) 808-5540; Raymond Costantino, Park Planning and Development Services Manager, (916) 808-1941, Department of Youth, Parks, & Community Enrichment

Body
Presenter: None

Attachments:
1-Description/Analysis
2-Contract
3-Resolution



Description/Analysis

Issue Detail: The Department of Youth, Parks & Community Enrichment (YPCE) is seeking approval to award a contract to Marina Landscape, Inc. for the Meadows Community Park Phase 1 project. Meadows Community Park is a 11.2-acre community park located at 1840 North Breezy Meadows Drive in Community Plan Area 10, Council District 1. The contract amount is $2,360,400. The improvements will consist of development of a playground with shade structure, group picnic area with shade structure, open turf area, concrete walkways, site furnishings and landscaping.

The formal bid process for this project has been completed and Marina Landscape, Inc has been selected as the lowest responsible and responsive bidder.

Construction of the Meadows Community Park Phase 1 is expected to be completed in Fall 2020.

Policy Considerations: City Code Chapter 3.60 provides that City Council approval is required to enter into construction agreements over $100...

Click here for full text