Title: Suspend Competitive Bidding and Supplemental Agreement: Broadway/Alhambra Navigation Center (C15001100) (Two-Thirds Vote Required)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title:
Title
Suspend Competitive Bidding and Supplemental Agreement: Broadway/Alhambra Navigation Center (C15001100) (Two-Thirds Vote Required)
End

FileID
File ID: 2020-00139

Location
Location: 2970 X Street, District 5

Recommendation:
Recommendation
Pass a Motion by two-thirds vote: 1) suspending competitive bidding in the best interests of the City and authorizing use of an alternative procurement method for selection of the construction contractor for the Broadway/Alhambra Navigation Center Project (C1501100); 2) authorizing the City Manager or the City Manager's designee to execute Supplemental Agreement No. 1 to Contract No. 2020-0110 with Zenith Engineers, Inc. for design and construction management of the Broadway/Alhambra Navigation Center Project in an amount not to exceed $65,000, for a revised total contract amount not to exceed $149,975; and 3) resetting the City Manager's authority to issue supplemental agreements for Contract No. 2020-0110.

Contact: Mark C. Brown, Supervising Engineer (916) 808-7118; James Christensen, Facilities Manager (916) 808-5863, Department of Public Works
Body

Presenter: None

Attachments:
1-Description/Analysis
2-Supplemental Agreement No. 1 with Zenith Engineers, Inc.



Description/Analysis

Issue Detail: On August 27, 2019, City Council passed a Motion approving Addendum No. 1 to the Homeless Services Funding plan, which established priorities for funding of navigation centers and other services for people experiencing homelessness. This plan included the design and construction of the Broadway/Alhambra Navigation Center located at 2970 X Street ("Broadway/Alhambra Center").

On December 10, 2019, to streamline the design and construction process for the Broadway/Alhambra Center, City Council adopted Resolution No. 2019-0467, suspending competitive bidding and authorizing use of the design-build delivery model for design and construction of the Broadway/Alhambra Center, and authorizing a design-build con...