Title: Change Order: Sacramento Water Treatment Plants Rehabilitation Project Phase 2 Improvements
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title:
Title
Change Order: Sacramento Water Treatment Plants Rehabilitation Project Phase 2 Improvements
End

FileID
File ID: 2020-00225

Location
Location: Districts 3 and 6

Recommendation:
Recommendation
Adopt a Resolution: 1) authorizing the City Manager or the City Manager's designee to execute Change Order No. 1 to City Agreement No. 2019-1570 with TNT Industrial Contractors, Inc. (TNT), for an amount not-to-exceed $167,352, bringing the agreement's total not-to-exceed amount from $1,301,738 to $1,469,090; 2) resetting the City Manager's administrative authority to issue Change Orders for Agreement No. 2019-1570, and 3) transferring $90,000 from the Base CIP Contingency - Water (Z14000700, Fund 6005) to the Treatment Plant Rehab Design (Z14006000, Fund 6005).

Contact: Megan Thomas, Project Manager (916) 808-1729; Michelle Carrey, Supervising Engineer (916) 808-1438; Tony Bertrand, Engineering & Water Resources Division Manager, (916) 808-1461; Department of Utilities

Body
Presenter: None

Attachments:
1-Description/Analysis
2-Change Order No. 1
3-Resolution


Description/Analysis

Issue Detail: Staff recommends Council approve Change Order No. 1 with TNT for City Agreement No. 2019-1570, to install a structural wall to address unanticipated corrosion impacts to the structural integrity of existing bulkheads in the grit basin of the E. A. Fairbairn Water Treatment Plant (FWTP). The plant must be out of service to complete the work. As this work is similar in nature to other structural walls built as part of the existing contract, the proposed change order would ensure the repair is completed during the shutdown window without impacts to the City of Sacramento (City) water system.

Policy Considerations: This Change Order exceeds the City Manager's approval authority and requires Council approval.

Economic Impacts: This Change Order is expected to create 0.67 total jobs (0.39 direct jobs and 0.28 jobs through indirect and induced activit...