File #: 2020-00239    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 2/12/2020 In control: City Council - 2PM
On agenda: 3/10/2020 Final action:
Title: Contract: REBID- Freeport Blvd., 56th Avenue and Pleasant Drive Pipe Replacement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title:
Title
Contract: REBID- Freeport Blvd., 56th Avenue and Pleasant Drive Pipe Replacement
End

FileID
File ID: 2020-00239

Location
Location: Citywide

Recommendation:
Recommendation
Pass a Motion: 1) approving the contract plans and specifications for the REBID - Freeport Blvd., 56th Avenue and Pleasant Drive Pipe Replacement Project; and 2) awarding the contract to Express Sewer and Drain, Inc. for an amount not-to-exceed $177,580.

Contact: Sonia Lopez, Associate Engineer (916) 808-1456; Tony Bertrand, Engineering & Water Resources Division Manager, (916) 808-1461; Department of Utilities

Body
Presenter: None

Attachments:
1-Description/Analysis
2-Contract



Description/Analysis

Issue Detail: Staff recommends Council award a construction contract to Express Sewer and Drain, Inc., to replace approximately 520 lineal feet of 6-inch sewer pipeline, using pipe bursting techniques. Included in the scope of work is the construction of equipment launching pits, restoration of manholes, and replacement of sewer services

Policy Considerations: City Council approval is required to award construction contracts of $100,000 or more. The action requested conforms with City Code Chapter 3.60, Articles I and III, which provide for award of competitively bid contacts to the lowest responsible bidder. The replacement and rehabilitation of aging and deteriorated sewer pipes is consistent with the criteria set forth in the Department of Utilities' Capital Improvement Programming Guide to replace and expand critical infrastructure to ensure reliability and safety of the City's sewer system.

Economic Impacts: This project is expected to create 0.71 total jobs (0.41 direct jobs and 0.30 jobs through indirect and induced activities) and create $109,644.11 in total economic output ($69,109.52 of direct output and another $40,534.59 of output through indirect and induced activities).

The indicated economic impacts are estimates calculated using a calculation ...

Click here for full text