Title: Approve Supplemental Agreement and State Baseline Agreement for Grant Funds, and Budgetary Adjustments - I Street Bridge Replacement Project (T15136000) [Published for 10-Day Review 04/01/2021]
Indexes: Budget Change, Report Submitted Late
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title:
Title
Approve Supplemental Agreement and State Baseline Agreement for Grant Funds, and Budgetary Adjustments - I Street Bridge Replacement Project (T15136000) [Published for 10-Day Review 04/01/2021]
End

FileID
File ID: 2021-00120

Location
Location: A new bridge crossing of the Sacramento River at Railyards Boulevard upriver from the I Street Bridge, and the upper deck of the I Street Bridge, Districts 3 and 4

End
Recommendation:
Recommendation
Adopt a Resolution authorizing the City Manager or the City Manager's designee to: 1) execute Supplemental Agreement No. 28 to City Agreement No. 2014-0244 with Mark Thomas & Company, Inc. in an amount of $8,623,456, for a new not-to-exceed amount of $14,142,229 and extend the duration of the professional services agreement to December 31, 2023; 2) execute a Project Baseline Agreement with the California Transportation Commission (CTC) and the California Department of Transportation; 3) increase the revenue and expenditure budgets in the I Street Bridge Replacement Project (T15136000) by $11,442,650 (Federal Capital Grants, Fund 3703); 4) transfer $1,488,691 (Major Street Construction, Fund 2007) from the expenditure budget in the State and Federal Grant Match Program (T15007200) to the expenditure budget in the I Street Bridge Replacement Project (T15136000); and 5) reset the City Manager's authority to issue supplemental agreements for City Agreement No. 2014-0244.
FileName

Contact: Jesse Gothan, Supervising Engineer (916) 808-6897; Nader Kamal, Interim
Engineering Services Manager (916) 808-7035, Department of Public Works
Body

Presenter: None

Attachments:
1-Description/Analysis
2-Resolution
3-Mark Thomas Supplemental Agreement No. 28
4-Baseline Agreement for Local Partnership Program Funds



Description/Analysis

Issue Detail: On February 21, 2020, the City hosted a public meeting at the Kaiser DOCO to announce the "Spring" design concept to advance to construction plans for the new bridge....