File #: 2019-00485    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 3/21/2019 In control: City Council - 5PM
On agenda: 5/28/2019 Final action:
Title: Contract: Barandas Park Phase 2 Project
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title:
Title
Contract: Barandas Park Phase 2 Project
End

FileID
File ID: 2019-00485

Location
Location: District 4

Recommendation:
Recommendation
Adopt a Resolution: 1) approving the construction plans and specifications for the Barandas Park Phase 2 Project (L19108100); 2) approving the transfer of $106,000 Quimby funds to the Barandas Park Phase 2 Project (L19108100) from the Quimby In-Lieu (Fund 2508) Available Fund Balance; 3) awarding the contract for the project to Sierra Valley Construction Inc. in an amount of $353,356; and 4) authorizing the City Manager or City Manager's designee to execute the contract.

Contact: Dennis Day, Landscape Architect, (916) 808-7633; Raymond Costantino, Division Manager, (916) 808-1941; Park Planning and Development Services; Department of Youth, Parks, & Community Enrichment

Body
Presenter: None

Attachments:
1-Description/Analysis
2-Resolution
3-Contract




Description/Analysis

Issue Detail: The Department of Youth, Parks, & Community Enrichment is seeking approval to award a contract to Sierra Valley Construction Inc. for the Barandas Park Phase 2 Project. Sierra Valley Construction Inc. was the low bidder and the contract amount is $353,356. The work will include clearing and grubbing, grading and drainage, concrete flatwork, concrete mow strips, concrete pads, aggregate base, decomposed granite paving, rule signage, chain link fencing and gates, drinking fountains, concrete benches, trash receptacles, automatic irrigation system, shade trees and a plant establishment period. Construction is expected to be completed by year end 2019.

Manuel Barandas Park is a 11.3-acre community park located at 2805 Grasslands Drive, in Council District 4.

Policy Considerations: The City Manager is authorized to make appropriation changes not exceeding $100,000 by fund from available fund balance per City Budget Resolution No. 2018-02535, Section 6.3. Appropriation changes that exceeding $100,000 from a fund balanc...