Plans and Specifications and Contract Award: Midtown Streetlighting Phase III Project (T15175200)
End
FileID
File ID: 2019-00894
Location
Location: 17th Street, 18th Street, and 19th Street between G Street and J Street, District 4
Recommendation:
Recommendation
Pass a Motion: 1) approving the Plans and Specifications for the Midtown Street Lighting Phase III Project (T15175200); 2) awarding the construction contract for the Midtown Street Lighting Phase III Project (T15175200) to Pacific Excavation Inc. for an amount not to exceed $397,769; and 3) authorizing the City Manager or the City Manager's designee to execute the construction contract for the Midtown Street Lighting Phase III Project (T15175200).
Contact: John Matoba, Associate Electrical Engineer, (916) 808-7891; Judy Matsui-Drury, Supervising Engineer, (916)-808-7610; Nader Kamal, Interim Division Manager, (916) 808-5065, Department of Public Works
Body
Presenter: None
Attachments:
1-Description/Analysis
2-Plans
3-Construction Contract
Description/Analysis
Issue Detail: In 2014, Midtown Street Lighting Phase I installed new ornamental streetlights on J Street between 20th Street and 27th Street. In 2017, Midtown Street Lighting Phase II installed new ornamental streetlights on 21st Street, 22nd Street, 23rd Street, 24th Street, and 25th Street between J Street and K Street.
The Midtown Street Lighting Phase III Project will expand pedestrian-level street lighting on 17th Street, 18th Street, and 19th Street between G Street and J Street. The improvements include new ornamental streetlights with energy-efficient LED lighting and new underground infrastructure. This project is funded with Community Development Block Grant (CDBG) funds administered by the Sacramento Housing and Redevelopment Agency (SHRA).
On April 23, 2019, City Council approved the award of the streetlight pole procurement contract for this project.
On April 29, 2019, the construction contract was a...