City of Sacramento header
File #: 2020-00199    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 2/5/2020 In control: City Council - 2PM
On agenda: 3/10/2020 Final action:
Title: Change Order: Department of Utilities 35th Avenue Demonstration Garden Project
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title:
Title
Change Order: Department of Utilities 35th Avenue Demonstration Garden Project
End

FileID
File ID: 2020-00199

Location
Location: District 5

Recommendation:
Recommendation
Pass a Motion: 1) authorizing the City Manager or the City Manager's designee to execute Change Order No. 3 in an amount not to exceed $24,534 to Contract No. 2019-0712 with Sierra Valley Construction, Inc. bringing the agreement's total not-to-exceed amount to $723,773; and 2) ratifying Change Orders No. 1 and 2 to Contract No. 2019-0712; and 3) resetting the City Manager's authority to issue change orders for the Contract.

Contact: Kevin Love, Facilities Program Manager, (916) 808-5592; Department of Public Works; Roshini Das, Sustainability Program Manager (916) 808-6270; William O. Busath, Director, (916) 808-1434; Department of Utilities.

Body
Presenter: None

Attachments:
1-Description/Analysis
2-Change Order No. 3



Description/Analysis

Issue Detail: Staff recommends the City Council (Council) approve Change Order No. 3 in the amount of $24,533 with Sierra Valley Construction, Inc. for the City Agreement No. 2019-0712, to accommodate the discovery of an irrigation mainline point of connection; the extension of a 12-inch drain line; repairs to the building downspouts along the east wall; and the realigning of the pedestrian walkway leading to the public right of way. Furthermore, ratification of Change Orders No. 1 and 2 are necessary to reset the City manager's authority.

Policy Considerations: This Change Order exceeds the City Manager's approval authority and requires Council approval.

Economic Impacts: The recommended Change Order is expected to create 0.1 jobs (0.1 direct job and 0.0 jobs through indirect and induced activities) and create $15,148 in total economic output ($9,548 of direct output and another $5,600 of output in indirect and induced activities).

Environmental Considerations: The proposed project has been determined to be exempt fro...